Park West CC(02-2)-CS050707 (3)July 7, 2005
PK No.: 1628-05.034
Mr. Keith R. Marvin, P.E.
CITY OF COPPELL
255 Parkway Bouleva~
Coppell, Texas 75019-4409
Re:
PARKWEST COMMERCE CENTER
Coppell, Texas
Dear Mr. Marvin:
This letter is to notify you that the enclosed Construction Plans have been revised in
accordance with your June 29, 2006, Review Memorandum. The following items have
been addressed as per the referenced review:
GENERAL COMMENTS
· I see in your response letter that you have forwarded your documents to the gas
company for review. Prior to constructing anything within that 50' easement we will
need a copy of the documentation allowing the construction.
Response: As previously discussed the Owner is resolving the issue.
· There was a question regarding the depth of water within the fire lane between the
two buildings, I see that you have revised the storm sewer to remove the bypass,
however, your hydraulic grade line still shows a depth of water within the fire lane.
Please provide documentation on that depth.
Response: Per storm system design the storm water depth will not exceed 6"
in the truck court. Note added to plans.
· I reviewed your request for a variance from the lime stabilization requirement. Your
request is acceptable within the private paving areas of the project, however we do
require either lime stabilization or compacted flex base under paving in the right-of-
way. That would include the proposed left turn lane and the three proposed drive
approaches.
Response: Plans have been revised as requested.
If you have any questions or need any additional information, please call at your earliest
convenience.
Sincerely,
SAM/jpm
1628-3O3
cc: Glenn Denham - Cadence McShane Group