DR0401-CS050722July 22, 2005 Kay Keene, President Whitewater Construction, Inc. 6640 Old Mexia Rd Waco TX 76705 COl'FELL RE: Oakcrest Barrow Ditch Drainage Improvements Project # DR 04-01 - Request for Change Order Dear Ms. Keene: This letter is the response to your request for a Change Order to add calendar days to your contract and to change the pipe specified from RCP to ADS. My answer is multi-part, so I will respond as you have posed the issues: 1) As to the slow process of hand digging - the City will take your request to add days under advisement. You should continue to work diligently to complete the contract under the stated terms. If the work proceeds and we see that hand digging is inordinately cumbersome and time consuming, we will consider adding some days to the contract. 2) As discussed onsite, our intent was to meander the ditch line to avoid disturbing existing improvements. This should be the tactic you use to work around those improvements such as mailboxes and landscaping. Work with the City Inspector to disrupt as few improvements as possible. You are correct in your assessment that Whitewater will not be paid for line items not constructed. This is a unit price contract, and the final payment will be based on the actual quantity constructed at the contract unit price. 3) We will consider the use of ADS pipe in lieu of RCP with the appropriate reduction in cost per LF connected with the difference in price. Please submit an estimate of the difference and we will consider issuing a change order. In lieu of a cost reduction we would also con:sider the addition of an appropriate end treatment for the culverts. If you have any further questions or want to discuss these matters, please contact me at the number below. Sincerely, Keith R. Marvin, P.E. Civil Engineer Office 972/304-7044 Fax 972/304-3570 kmarvin~ci.coppell.tx .us cc: ~a~eth CampbelL. Con~tmclicmJnspector