SS9901-CN050712July 12, 2005 T H E · C I ? Y · 0 F COP?ELL Robbie Dupree, Dallas Division Vice President MasTec North America, Inc. 4747 Irving Blvd., Suite 221 Dallas, TX 75247 FAX 214/571-2565 Deforest Road Lift Station Improvements Force Main Line "D" Project # SS 99-01 Change Order//5 Dear Mr. Holland: Attached are three original Charge Order//5 documents for the construction of the vault as has been discussed on the referenced project. Please execute the documents and return two of the originals to me. One of the originals is for your file. If you have any questions please feel free to give Rick O'Dell, Construction Inspector, a call at 972/304-7090. Sincerely, Kenneth M. Griffin, P.E. Director of Engineering/Public Works Office 972/304-3686 Fax 972/304-7041 E-mail kghffin@ci.coppell.tx.us PROJECT: CONTRACTOR: OWNrER: CHANGE ORDER NO.: CITY OF COPPELL CHANGE OR EXTRA WORK ORDER Deforest Road Lii~ Station Improvements Force Main Line MasTec North America, inc. City of Coppell Five (5) DATE: 7/11/05 Item Description Additional labor and equipment for construction of vault that replaced 30" Gate Valve deleted in Change Ord//2 includes: Additional Material Costs Labor Excavator Front End Loader Pick Up Total Revision to Contract Amount Quantity Unit Unit Price Total 1 LS 606.00 606.00 4 DAYS 822.25 3,289.00 3 DAYS 365.00 1,095.00 3 DAYS 180.00 540.00 4 DAYS 55.00 220.00 $5,750.00 Original contract amount Net Increase in contract amount Change Order #1 Net Decrease in contract amount Change Order #2 Net Increase in contract amount Change Order #3 Net Increase in contract amount Change Order #4 Net Increase in contract amount Change Order/45 Revised contract amount Net increase in contract time of completion Revised Contract time of completion $ 2,364,835.54 $1,350.00 ($ 32,330.70) $ 5,907.00 $ 9,631.00 $5,750.00 $ 2,355,142.84 5 DAYS 305 DAYS The contractor hereby accepts this Contract adjustment as a final and complete adjustment in full accord and satisfaction of all past and future liability originating under any clause in the Contract by reason of this revision to the Contract. RecommendelJ qy City Engineer Date Accepted by City Date Agreed to by Contractor Date · a sTe c July 8, 2005 ML Rick O'Del! Construction Inspector City of Coppell, Texas 255 Parkway Blvd. CoppelL Texas 750~0, Re: ocForest Ro. L. tt Station !mproyemcmts Force Main l,ine D Change Order Nc 5 !he rcl:krcu,zed 5re:j,:': ;n::luded tli;'ee da:~s labor ~nd equipment ?ace the 5(7' ~::'.12 qatve aha maaho[e stmclure. Howeser, the :< this Iocatin:; m~uJred an additional five da:.~: labor and · pota' ihe Eottor:~ a,::l r~rst Four (eot of vertical Additilm,d Mauzi?.! C(,,t i LS fi0'.~.LC 606.00 Labor 4 DAYS 822.25 3,289.00 Excavator 5 DAYS 365.t)0 ! .095.00 Front End Loader 3 DAY S 1 g0.00 540.00 Pick Up 4 DAYS 55.00 220.00 Respectfhl y submitted, Mastec North America Dallas Division Vice President MasTec North America, Inc 4747 Irving Blvd, Suite 221 Dallas, Texas 75247 · 2145712500 fax2145712555 wwwmasteccom · :M a sTe c July 6, 2005 Mr. Rick O'De!! Construction Inspector City of Coppell, Texas 255 Parkway Blvd. Coppell, Texas 75019 Re: DeForest Rd. Lift Station Improvements Force Main Line D Change Order No. 5 O Dell. Dear Mr. ' · The original estimme for the referenced project included three days labor and equipment to form, pour the footing, place the 30" gate valve and manhole structure. Bowever, the vault that was required at this location required an additional five days labor and equipment to form and ~cour thc bosom mid first four feet of iertical wall. Accordingly, we respectfully request an increase in our contract to compensate ~br th~s dit'f~rence as lbliows: Additional Material Cost I LS Labor 5 DAYS Excavator 5 DAYS Front End Loader 5 DAYS Pick Up 5 DAYS Total. R~:que~tcd l~creasc Respectfully submitted, Mastec North America Dallas Division Vice President MasTec North America, Inc. 4747 Irving Blvd., Suite 221 Dallas, Texas 75247 '"""214.5712500 fax214571.2555 www.masteccom 3,860.00 3,860.00 822.25 4,11 ! .25 365.00 1,825.00 ! 80.00 o00.00 55.00