SS9901-CS040621 (3)Turner Collie f._ Braden Inc.. TRANSMITTAL
To:
From:
Date:
Job No.:
Subject:
See Distribution
George Cisneros, P.E. - TCB
June 21, 2004
052 131124.0001 04000.A123 (2.1)
Deforest and Sandy Lake Wastewater Litt Stations and Force Main Improvements
Force Main Line D
Shop Drawing Review Comments
Submittal No. 2
TCB has the following comments on this submittal:
Description Status Comment
Precast Manhole No Exceptions Taken
MH Pipe to Manhole Per conversation with Mastec, connector
Connector boots will not be needed for the project;
MH Rubber Gasket for No Exceptions Taken Per City's direction, previously submitted
Section Joints gaskets are approved;
Trench Excavation & Received
Shoring Safety Plan
Training Certification Submit Specified Item Required per Specification Section 02643;
in HDPE Fusion
Joining
30" Gate Valve No Exceptions Taken Per plans, gate valve is to be installed
vertically;
4000 psi Concrete No Exceptions Taken
Batch Design
Mastec 24 Hour Received
Contact List
Subcontractor Contact Received
List
Traffic Control Plan Received
Project Schedule Received
When you re-submit the shop drawings, please address all comments and submit seven (7) copies to
this office.
Distribution: [X] 2 copies of submittal to the City
[X] 4 copies of submittal to Mastec
[X] 1 copy of submittal to TCB file
[ ] Other