ST9904-CS000711July 11,2000
Mr. Jim Witt
City Manager
City of Coppell
P. O. Box 478
Coppell, Texas 75019-0478
0°0
L CITY OF COP~'LL
RE: Joint Funding of SH 114/121 Schematic Alternative Development
Dear Jim:
In accordance with conversations between our respective staffs, I am submitting
this letter agreement for your execution.
The Cities of Coppell and Grapevine agree to cooperate in the preparation of an
alternative access schematic study for the SH 121 corridor from 1-635 to Denton
Creek by Parsons Transportation Group. This undertaking is part of a larger
scale study being pursued by the City of Grapevine for the entire MIS corridor.
The cities agree that the cost participation by the City of Coppell shall not exceed
$10,000 without written approval by the City of Coppell. The City of Coppell will
submit payment to the City of Grapevine in the full amount with this executed
letter agreement. Upon completion of the study, final costs shall be determined
for this Denton Creek to 1-635 segment of the complete study. The City of
Coppell's proportionate share of any balance attributable to this segment of the
study shall be refunded by the City of Grapevine within 60 days of final approval
of the study.
Sincerely,
ROger ¢lelson
City Manager
City of Grapevine
Accepted:
Ji,~
~c~tY Manager
ty of Coppell
O:\stan\114_121MIS\Coppell_Letter_Agmnt
City Manager's Office · EO. Box95104 · Grapevine. Texas 76099 · 817-410-3104 · Fax 81%410-3002 · http://www.ci.grapevine.tx.us
86/89/2888 11:59
817 41~ 3003
817-410 ' ~3 CITY OF GRAPEV~
PAGE 01
PARSONE
June 8,2000
Jerry Hodge
Director of Public Works
City of Grapevine
P.O. Elox 95104
Grapevine, TX 76099
Re: SIll 14/121 Schematic Alternative Development
Dear Jerry:
AS requested, we have reviewed our proposal to identify the amount of our overall effort that will
address the City of Coppell's concerns in regard to interchange issues at Sandy Lake Road and
at BassPro Drive/Bethel Road I estimate that the issues constitute between $9,000 and $10,000
of our project effort,
If additional information is needed, let me know
Sincerely,
I~AR~CIN=: TRANSPORTATION GRClUf~ INr.
Robed W Jenkins, P.E.
Area Manager/Principal Associate
PARSONS
Barton-Aschman Associates, Inc. · A Unit of Parsons Transportation Group, Inc.
2630 West Freeway · Suite 132 · Fort Worth · Texas · 76102 USA, (817) 877-5803 ° (817) 877-3214 fax
June 8, 2000
Jerry Hodge
Director of Public Works
City of Grapevine
P.O. Box 95104
Grapevine, Texas 76099
Re: SHt ~4/t2 ~ Schematic Alternative Development
Dear Jerry:
In follow-up to our meeting with TxDOT and HDR on May 5, 2000, Parsons Transportation Group Inc. is
pleased to submit this proposal to provide professional traffic engineering and roadway design services in
connection with the City's efforts to optimize the SH114/SH121 MIS schematic in serving both regional
traffic and local access. We understand that the City is concerned about HDR's proposed schematic as it
currently exists. The exisfing access to the Mills Mall and to the Bass Pro area as well as the important
functions that SH 26 and Bus 114 (LP 382) will play in providing access to this important growth area of the
City are not adequately addressed in the current schematic. The purpose of this alternative design study
will be to develop and evaluate alternatives that will best provide for the existing and expected local access
requirements while providing for regional travel needs.
If accepted, this letter will become an agreement between the City of Grapevine (GV) and Parsons
Transportation Group Inc. (PTG) to provide the scope of services outlined below.
Scope of Services
1. Gather available traffic assignment, mapping, and design data/drawings from HDR team.
2. Review available data and determine additional data needs. Secure additional available data.
3. Identify perceived deficiencies of proposed schematic for remainder of corridor (west of Business 114
interchange). Prepare annotated list for HDR to allow parallel resolution by HDR team.
4. Review existing traffic assignment to understand relative traffic flow and basis for HDR proposal.
5. Brainstorm solution options for interchanging between Bus 114 (LP 382) and Grapevine Mills
Parkway (FM 2499)/Grapevine Mills Parkway North/Sandy Lake Road area.
6. Develop conceptual drawings for promising alternatives.
7. Review new traffic assignment by TxDOT when available.
8. Manually reassign traffic to alternatives and evaluate operations.
9. Refine conceptual alternatives.
10. Review alternatives with City and select preferred alternative(s).
11. Simulate operations with preferred alternative(s).
12. Present selected alternatives with simulation to TxDOT and HDR team.
13. Assist HDR team with refinement of agreed to solution alternatives.
14. Review and critique refinements addressed by HDR team for deficiencies defined in Item 3 above.
15. Document by technical memorandum findings and resolution.
Additional Services
Any additional services beyond the scope of this Agreement would be covered by a written supplemental
agreement to include council presentations.
Deliverables
Task
1 -10
11 -12
15
Alternative drawings for discussion
Selected conceptual drawings and simulation results for discussion with TxDOT and HDR
Technical Memorandum to present summary of resolulJon findings.
Infonmation and Services to be Provided by GV
1. Discussion of City objectives and understanding
2. Facilitating coordination with TxDOT and HDR
3. Review comments and assistance with preferred alternative consideration and selection
Fee for Services and Method of Payment
PTG shall be compensated for services rendered on an hourly basis plus expenses. This amount will not
exceed $52,800 unless authorized by supplemental agreement.
Billings are due and payable within thirty (30) days of invoice date.
Time of Performance
Task I Wkl I Wk2 Wk3 Wk4* Wk5 Wk6 Wk7 Wk8 Wk9
1
2
3
5
~3
*Assumes revised assignment from TxDOT has been received.
Task 13 will be accomplished within two weeks of completion of Task 12, unless othenvise agreed.
Termination
GV and PTG will have the right to terminate this Agreement by written notice to the other party. In such
event, all finished and unfinished documents and work papers prepared by PTG under this Agreement will,
at the option of GV, become the City's property and PTG will be paid all costs incurred for services
rendered up to the date of such termination.
Indemnification
In the event of a willful or negligent act or omission by a party to this Agreement, that party will hold the
other harmless from and against any damage, claim, or loss resulting to the other therefrom.
Authorization
PTG is prepared to initiate work on this assignment upon receipt of a signed copy of this Letter of
Agreement. This proposal will be valid for thirty (30) days.
We appreciate this opportunity to work with you on this assignment. If you have questions regarding this
proposal, please let me know.
Sincerely,
PARSONS TRANSPORTATION GROUP INC..
Robert W. Jenkins, P.E.
Principal Associate and Area Manager
ACCEPTED AND APPROVED BY:
(Signature)
(Typed or printed name)
(Title)
AUTHORIZED TO EXECUTE AGREEMENTS
FOR: The City of Grapevine
(Date)
Vendor #:
Pay
Address:
CrrY OF COPPELL
PAYMENT AUTHORIZATION MEMO
(Do not. se mi 'als~acro ym~/abbrev~htio
q~d-~pt-Division-Expen~ Code)
Descriptio~xpl.ation: ! ~ ,~, , f'[ 1~
Approval
Date:
ACCOUNTING USE ONLY
Approved for payment by:
Date Paid
Cheek Number
havoiee No.