Freeport NIP(8.1)-CS050728DEVELOPMENT REVIEW COMMITTEE
ENGINEERING COMMENTS
1TEM:
PD-186R7-LI~ Duke-Freeport, zoning change request from PD-186R2-LI
(Planned Development-186 Revision 2-Light Industrial) to PD-186R7-LI
(Planned Development-186 Revision 7-Light Industrial), to attach a Detail Site
Plan to Lots 2R1 and 2R2, Block A, to allow the construction of a 142,247-
square-foot building on Lot 2RI and a 93,345-square-foot building on Lot 2R2,
totaling approximately 15.51 acres of property located along the north side of
Bethel Road, west of Freeport Parkway, at the request of Brian Straley, Duke
Realty Corporation.
STAFF REP.: Gary Sieb PROJECT ID# PD-05-0031
DRC DA TE: July 28, 2005 and August 4, 2005
CONTACT: Kenneth M. Griffin, P.E., Dir. of Engineering/Public Works 972/304-3686
COMMENT STATUS: ,/PRELIMINARY FINALt RE!7!SED
rrvn P&Z
Detailed Site Plan
1. Show the bands of stamped concrete at entryways along Bethel Road and Freeport
Parkway, as well as the stamped concrete in the median noses in the left turn bays on
Freeport Pkwy.
2. Show relocation of the light standards on Freeport Pkwy.
3. No median openings are currently proposed (or shown) to serve any of the drives en
Bethel Rd. Are you requesting any?
4. Ensure the proposed sidewalks are ADA compliant.
5. Ensure that adequate right-of-way is provided for the construction of the 8' Hike &
Bike trail. Cost of construction of a 5' sidewalk should be placed in escrow with the
City and will be used to construct the Hike & Bike trail.
DEVELOPMENT REVIEW COMMITTEE
ENGINEERING COMMENTS
ITEM:
Duke-Freeport Addition, Lots 2R1 and 2R2~ Block At Replat, being a replat
of the remaining portion of the original Lot 2, Block A, to allow the
construction of a 142,247-square-foot building on Lot 2R1 and a 93,345-
square-foot building on Lot 2R2, totaling approximately 15.51 acres o~'property
located along the north side of Bethel Road, west of Freeport Parkway, at the
request of Brian Straley Duke Realty Corporation.
STAFF REP.: Gary Sieb PROJECT ID//RP-05-0032
DRC DATE: July 28, 2005 and August 4, 2005
CONTACT: Kenneth M. Griffin, P.E., Dir. of Engineering/Public }Vorks 972/304-3686
COMMENT STATUS: ,/PRELIMINARY F!.nLA~L P~V!£ED
A ..... P&Z
Replat
1. Show the curves (C1-C10) and lines (L1-L2) listed in the tables. Do these curves and
lines define the fire lanes? If not, define curves and lines in the fire lanes.
2. The 25'X25' water easements should be made larger to accommodate the vaults
without encroaching on the franchise utility easements.
3. Define the locations water easements using a line table or call-outs.
4. The Fire Lane should also be called a Mutual Access Easement.
Paving Plan
1. How do the proposed storm sewer connections to the future Bethel Road
improvements impact the design of the future 21" RCP Storm Drain? How does the
proposed storm sewer system impact the design of the Freeport detention basins?
Show drainage areas and calculations. Propose the system so there are no adverse
impacts.
2. How will the proposed storm drain system work until the Bethel Road improvements
are in place?
Water & Sewer Plan
1. Clarify the unconnected "Proposed 8" Fire Service" that crosses the fire lane
between the buildings.
2. Place an 8" valve between the vault and the water meters.
3. Do not place vault and meters inside the "TXU" Easement.