SS9901-CS050825August 25, 2005 CO?FELL Canfer Construction Company, Inc. Charlie A. Ferrara, Vice President 11031 Grissom Lane Dallas, TX 75229 FAX 972/484-4223 Deforest & Sandy Lake Wastewater Lift Stations Project # SS 99-01 Change Order # 2 Dear Mr. Ferrara: Attached are three original Charge Order #2 documents for the revised wall design at the Deforest Road Lift Station as has been discussed on the referenced project. Please execute the documents and return two of the originals to me. One of the originals is for your file. If you have any questions please feel free to give Rick O'Dell, Construction Inspector, a call at 972/304-7090. Sincerely, Director of Engineering/Public Works Office 972/304-3686 Fax 972/304-7041 E-mail kgb ffin~ci.coppell.tx.us 255 pARKWAY ]Ir p O.E~OX 9478 1¥ COppELL TX 75019 1~' TEL 972/a62 0022 *' FAX 972/30zl 3673 From: 08/19/2005 02:16 ~79 P.002/005 Serial Letter No. Contract No. ~ 99-01 TurnerCol[le&Braden 17300 Dallaa Parkway Dallas.TX 75248 Comtract~r; CAN.FER Con,traction Company 11031 Grl~eom Lane Dalla6,~ ~5229 Change Order Propola1.0002 DeforeM Rd. & ~andy Lako Rd. Lift Station Impravementa Dat~: Augumt 18,200,5 Work Description: Install double wythe of brick et Deforest Rd screenwa[I TOTAL~i: CAN-FER Insurance 1 4% Subtotal Overhead(Home Office) - 8.5% Subco~trau-'ted Wor~ Profit SubcentracteCL Work 6.0% Subto~l Overhead(Home Office) - $.5%Self Performed Work Subtotal Profit-12% Self Performed Subtotal Bond ~ Total Subtotal Labor Material Equipment Subcontractor $ 2,s0,.. I $ .9.s21 $ I $ ~2,402.°°1 $15,800.4z $221.21 $f6,021.63 $1,361.54 $t7,383.46 $1,043,01 $'18,426,47 $0 O0 $0.00 ~0,00 $18,426.4/ , $294.82 ~181721.30 *** ~ day time extension.*** 98/19/2605 02:16 ~79 P.gO3/g65 NON.TAXED MATERIAL CITY UNIT UNiT PI~CB o .... T~ ~TE~ ~ UN~ ' UNIT ~ TOTA~ ..... o o So.oo ,- o From: 08/19/2005 02:17 ~79 P.004/005 FENIMORE-BLYTHE C o m m e r ~; i · t MII ~ o n r y CANFER Construction Co 11031 Grissom Lane Dallas TX 75229 8/17/05 Tel: 972-484-4344 Fax: 972-484-4223 Attn: Chariie Ferera Re: Project Deforest Lift Station Dear Charlie Re: Brick for Screen Wall & Screen Wall Design On Thursday 18th August 2005 Tommy, your field superintendent called and asked me to revise the Addition for Eight Columns in the wall. Attached is the adjusted price. The existing wall has two parallel skins of brick with a grouted reinforced core, an overall height of 6'-0" and a rowlock cap. The Columns are 2'-0" square on plan, 7'-0" high With a Cast Stone cap. I also assume that there is a reinforced CMU core to the Coltmms. To tkis end I have attached a change order request to reflect the variance in the work. I look forward to hearing from you in the near future. Yours truly, Alan Cook, VP Estimating 2300 Hi. ins Lane - Fort Worth, Texas 761II 817/834-6301 - Metro 817/589.0977 · Fax 817/589-2052 08/ 9/2005 02: ? P.005/005 FENIMORE-BLYTHE Co mmerl;iel M ewo n ry 18-Aug-05 Canfer Construction Co Affn; Chaflie Fere~a Project Manager 11031 GrJssom Lane Da,ss TX 75229 Sir PROJECT: LOCATION: Deforest Pump Station Coppell TX Tel 972-484-4344 Fax g72-484-4223 CO #1 Below you will find pricing to pedorm additional work on the above noted project. Description of change; Add for revised Screen Wall Deslgll with a maximum of Eight Columns, which allows for increased wall span between Columns, MEASURE LABOR L~._aO~ M&E MAT&EQU P SUPERVISION 21 HRS 23.5(; $ 494 0.00 $ $ 494 E~RICKL~YERS 96 HRS 22 0CSS 2,112 0.00 $ i $ 2,112 LABORERS 137 HRS 12.50 1,715 0.00 $ $ 1,713 iSAWMAN 0 HRS 22,00 $ 0,00 S $ OPERATOR 30 HRS 15.50 $ 465 0.00 $ $ 465 FORKLIFT 30 HR$ 0.00 $ 20.00 $ ak (difference btwn new & original) 36ZB E.A. 0,00 $ 0.45 $ 1,633 CMU 162 EA, 0,00 $ 1.15 $ 209 $ 209 Ad. Wire 300 ff 000 $ 04.~ Wire [dlff between 8" & 4") 900 Ii' 0.00 $ 0 It Cast Btone (dlff btwn new & ori~inal~ I Item 0 00 $ 430.0{: $ 430 $ 430 Saw 0 EA. 0.0~ $ 12.00 $ MORTAR 4 1,5 cyd O.OC $ 110,00 $ 457 $ 457 3ROUT ~ COle & wall 9 65 YARDS 0,0C $ 80.00 $ 772 $ 772 FRUCKING 0 LuMp SUM 0.0{~ $ 200.00 $ $ Scaffol~in~ Inow ~,.~,~u;d b s of wafll, 900 st 050 $ 0.50 $ 180 $ 181 SUB TOTAL $ 4,783 $ SUB TOTAL $ 11 PROFIT 5.00% $ 891 PLEASE SEND A CHANGE ORDER AS SOON AS POSSIBLE. SINCERELY. f FaNIMO~T~ Approved By Canfer Construction Aran Cbol~,J PROJECT MANAGER Date 2300 Higgins Lane · Fort Worth, Texas 761ll 817/834-630I · Metro 817/589-0977 . Fax 817/589-2052