WA0301-CN050829PROJECT:
CONTRACTOR:
OWNER:
CHANGE ORDER NO.: One (1)
CITY OF COPPELL
CHANGE OR EXTRA WORK ORDER
Loch Lane Water Line Installation # WA 03-01
Fox Contractors
City of Coppell
DATE: 8/23/05
DELETE:
ADD:
Item Description Quantity Unit Unit Price Total
I-5 N. Fire Hydrant Assembly (1) LS 3,900.00 (3,900.00)
I-7 Reconnect Existing Services (9) EA 250.00 (2,250.00)
I-8 Rep/Connect Short Services (1) EA 575.00 (575.00)
1-10 Rem/Replace Concrete Sidewalk (32) SF 5.75 (184.00)
1-14 Aband 2" WE (1) LS 1,500.00 (1,500.00)
1-4 S. Fire Hydrant Assembly 1 LS 3,000.00 3,000.00
I-7 Rep/Connect Long Services I EA 600.00 600.00
l-I 1 Rem/Repl Concrete Drive Way 17.5 SY 120.00 2,100.00
I-12 Rem/Repl Asphalt Paving 27 SY 110.00 2,970.00
Total Revision to Contract Amount $261.00
Previous contract amount
Net increase in contract amount
Revised contract amount
Net increase in contract time of completion
Revised Contract time of completion
$58,391.00
$261.00
$58,652.00
N/A
N/A
The contractor hereby accepts this Contract adjustment as a final and complete adjustment in full
accord and satisfaction of ail past and future liability originating under any clause in the Contract by
reason of this revision to the Contract.