June 2, 1998
Asbury Estates
Development Fee Assessment
Dear M Simmons:
Enclosed is a copy of the City of Coppell Development Fee Assessment table, along with a copy
of the Development Fee calculations for the referenced development.
Please make payment to the City of Coppell ia the amount of $43,685.00 and forward to the
Finance Department along with a copy of the Fee Assessment table. This amount is a portion
of the assessed fees which need to be paid prior to Council approval. Please refer to attached
table for additional fees. Also provide a copy of the Engineer's estimate or contract to our office
so the construction inspection fee can be verified.
Providing a copy of your paid receipt to the Engineering Depastutent will help us m verify the
payment of required fees and insure a successful beginning of this project. We look forward
to working with you on this project. If you have any questions, please contact me.
Michael A. Martin, P.E.
Assistant City Engineer
CC:
Jennifer Armstrong, Finance Director
Doug Stevens, Engineering Technician
Glenn Hollowell, Asst. Director of Public Works
Greg Jones, Chief Building Official
Gary Sims, Dir. Leisure Services
v'ELOPMENT FEE TABLE
Project: Asbury Estates
Date: 6/2/98
TOTAL AMOUNT DUE
FEES DUE PRIOR TO
COUNCIL
APPROVAL
Water Impact Fee $7,425.00 $7,425.00
(100% due prior to Council Approval)
Water Tap Inspection Fee $750.00
(100% due at Issuance of Water Meter)
Water Meter Fee (Domestic) $347.62
(100% due at Issuance of Water Meter)
Water Meter Fee (Irrigation/Fireline) $57.75
(100% due at Issuance of Water Meter)
Water Meter Deposit (Domestic) $490.00
(100% due at Issuance of Water Meter)
Irrigation/Fireline Meter Deposit $30.00
(100% due at Issuance of Water Meter)
Wastewater Impact Fee $6,300.00 $6,300.00
(100% due prior to Council Approval)
Wastewater Tap Inspection Fee $700.00
(100 % due at Issuance of Building Permit)
Utility Final Inspection Fee Il $700.00
(100% due at Issuance of Building Permit)
Park Fee $17,990.00 $17,990.00
(100% due prior to Council Approval)
Roadway Impact Fee $11,970.00 $11,970.00
(100% due prior to Council Approval)
Street Light Fee Information not
(100% due prior to Acceptance of Projec available at this time
Street Sign Fee Information not
(100% due prior to Acceptance of Projec available at this time
Construction Inspection Fee Need submittal of
development contracts
TOTAL $46,760.37
TOTAL AMOUNT DUE PRIOR TO COUNCIL APPROVAL $43,685.00
DEVELOPMENT FEE WORKSHEr- i'
PROJECT: Asbury Estates
DATE: 6/2/98
Water Impact Fee:
Domestic Meter(s):
Irrigation Meter(s):
Fireline Meter(s):
14 - 5/8 inch X 3/4 inch = 14
1 - 1 inch = 2,5
Total #: 16.5 ESU's @ $450.00 ea.
(100% due prior to Council approval of the final plat)
Water Tap Inspection Fee:
Total #: 15 Connections @ $50.00 ea.
(Single family due prior to issuance of building permit)
(All other developments due prior to issuance of meter)
Water Meter Fee (Domestic):
Total #: 14 Domestic Meter(s) @ '$24.83
(Single family due prior to issuance of building permit)
(All other developments due prior to issuance of meter)
Water Meter Fee (Irrigation/Fireline):
Total #: 1 Irrigation Meter(s) @
Total #: 0 Additional Irrigation Meter(s) @
Total #: 0 Fireline Meter(s) @
(100% due prior to issuance of water meters)
$57.75
Water Meter Deposit Fee (Domestic):
Total #: 14 Meter(s) @ $35.00 ea.
(100% due prior to issuance of water meters)
Irrigation/Fire Meter Deposit Fee:
Total #: 1 Meter(s) @ $30.00 ea.
(100% due prior to issuance of water meters)
Wastewater Impact Fee:
Total Domestic Meters ES
14
@ $450.00 ea.
Wastewater Tap Inspection Fee:
Total #: 14 Connections @ $50.00 ea.
(100% due prior to issuance of building permit)
Utility Final Inspection Fee (All developments):
Total #: 14 Lots @ $50.00 ea.
(100% due prior to issuance of building permit)
ESU's
ESU's
ESU's
ESU's
$7,425.00
$750.00
$347.62
$57.75
$0.00
$0.00
$490.00
$30.00
$6,300.00
$7OO.OO
$70O.OO
Page 1
DEVELOPMENT FEE WORKSHE~-T
Park Fee (For Residential Developments Only):
* Preliminary plat approved prior to June 23, 1992:
N/A
N/A
Single-family @ $150.00 / Lot
Multi-family @ $75.00 / Unit
(50% paid prior to Council approval of final plat)
(50% paid at issuance of building permit)
* Preliminary plat approved after June 23, 1992:
N/A
N/A
Single-family @ $350.00 / Lot
Multi-family @ $350.00 / Unit
(50% paid prior to Council approval of final plat)
(50% paid at issuance of building permit)
* Preliminary plat approved after October 26, 1993:
14
N/A
Single-family @ $1285.00/Lot
Multi-family @ $1285,00 / Unit
(100% paid prior to Council approval of final plat)
Roadway Impact Fee:
(See attached fee calculations)
Street Lighting Fees:
Assessed for lighting in the City's right-of-way,
This fee cannot be assessed until after T.U. Electric submits
the lighting plan for the proposed development.
Once the plans are submitted, $292.60 per light will be assessed.
(100% due prior to final acceptance of development)
Street Sign Fees:
Assessed for signage in the City's right-of-way.
(See attached fee calculations if applicable)
N/A
N/A
N/A
N/A
$17,990.00
N/A
$11,970.00
Information not
available at this time
Information not
available at this time
Construction Inspection Fees:
A copy of the development contract must be submitted for assessment.
The contracts should indicate the cost to construct the improvements
that are inspected by the Engineering Department.
(2% of development cost required for private improvements)
(4% of development cost required for public improvements)
Need submittal of
development contracts
Page 2
ROADWAY IMPACT FEE CALCULATIONS
PROJECT: Asbury Estates
DATE: 6/2/98
ROADWAY IMPACT FEI~:
Service Area * 1
~ategor7 ** Renidnnfial
Land Use ** Single-Family Detached
[~uildin~ Size (Sq. Ft.) N/A
Development Units ** 14
Vehicle Miles per Development Unit ** 2.85
Fee per Vehicle Mile *** $300
Roadway Impact Fee due = (Development Units) x
(Vehicle Miles per Developmem Unit) x (Fee per Vehicle Mile) = $11,970.00
* (Figure 2 - Roadway Impact Fee Study)
** (Table 3 - Roadway Impact Fee Study)
*** (Schedule 2, Page 3 - Roadway Impact Fee Study)