ST9703-CN050929 CITY OF COPPELL CHANGE OR EXTRA WORK ORDER PROJECT: CONTRACTOR: OWNER: MacArthur Boulevard Widening Project # ST 97-03 JRJ Paving, L.P. City of Coppell CHANGE ORDER NO.: Item 1-5 DELETE: One (1) Description Extension of Irrigation Conduit at Median Openings Bore Median Openings ADD: I-5A DATE: September 2, 2003 Quantity Unit Unit Price 1 LS 4,600 Total ($4,600) 1 LS 10,004 $10,004 Total Revision to Contract Amount $5,404 Previous contract mount Net increase in contract mount Revised contract amount Net increase in contract time of completion Revised Contract time of completion $319,988.85 $5,404.00 $325,392.85 N/A N/A The contractor hereby accepts this Contract adjustment as a final and complete adjustment in full accord and satisfaction of all past and future liability originating under any clause in the Contract by reason of this revision to the Contract. A¢¢~--~l~y City o~.~,, ~- Date Agreed to by Cont~ctor Date