Loading...
ST9902-CS051003COPPELL October 3, 2005 Mr. Mike Crawford AT&T Metro 4100 Bryan Street, Suite 615 Dallas, TX 75204 W. Sandy Lake Road ST 99-O2 A Utility Relocation Status Dear Mr. Crawford: This letter is a follow-up to the city's August 23, 2005 utility meeting regarding upcoming construction projects. The W. Sandy Lake Road project is scheduled to advertise in November 2005 with an anticipated construction start in January 2006. The right-of-way acquisition is complete and all conflicting utilities need to be relocated and/or adjusted prior to the construction start date. Utility companies are required to submi[ a Right-of-Way Use Permit along with three copies of the relocation plans to the Engineering Department for approval prior to starting the relocations. It is our understanding that AT&T Local Network Services has facilities within the project limits that will need to be relocated. These facilities will be relocated in conjunction with the AboveNet facilities. We have not received any relocation plans or any updates since the utility meeting and would appreciate an update on the submittal of relocation plans and the estimated start and completion dates of the relocations. Your consideration of this matter is appreciated. Should you have any questions or need any additional information, please advise. Sincerely, Suzal~l~aytor CIP C'~0rdinator Engineering Department Direct: 972-304-7019 Fax: 972-304-3570 E-mail: st aylor _(~ci.coppell.tx.us T H E - G I T Y 0 F C ?P-ELL October 3, 2005 Mr. Pete Nielson Senior Project Manager AboveNet 13647 Omega Drive Farmers Branch, TX 75244 RE: W. Sandy Lake Road ST 99-02 A Utility Relocation Status Dear Mr. Nielson: This letter is a follow-up to the city's August 23, 2005 utility meeting regarding upcoming construction projects. The W. Sandy Lake Road project is scheduled to advertise in November 2005 with an anticipated construction start in January 2006. The right-of-way acquisition is complete and all conflicting utilities need to be relocated and/or adjusted prior to the construction start date. Utility companies are required to submit a Right-of-Way Use Permit along with three copies of the relocation plans to the Engineering Department for approval prior to staJ-ting the relocations. It is our understanding that AboveNet has facilities within the project limits that will need to be relocated. These facilities will be relocated in conjunction with the AT&T Local Network Services facilities. We have not received any relocation plans or any updates since the utility meeting and would appreciate an update on the submittal of relocation plans and the estimated start and completion dates of the relocations. Your consideration of this matter is appreciated. Should you have any questions or need any additional information, please advise. Sincerely, Suzar) ]7aylor CIP Coordinator Engineering Department Direct: 972-304-7019 Fax: 972-304-3570 E-mail: sta¥1or('a)ci.coppell.tx, us T H E C I T Y · 0 F COP?ELL October 3, 2005 Ms. Karen Guiloreza Verizon 2094 McGee Lane Lewisville, TX 75077 RE: W. Sandy Lake Road ST 99-02 A Utility Relocation Status Dear Ms. Guiloreza: This letter is a follow-up to the city's August 23, 2005 utility meeting regarding upcoming construction projects. The W. Sandy Lake Road project is scheduled to advertise in November 2005 with an anticipated construction start in January 2006. All conflicting utilities need to be relocated and/or adjusted prior to the construction start date. Verizon submitted the Right-of- Way Use Permit and relocation plans in June 2004, and it is our understanding that some of the relocation work has been completed. We have not received a Completion Verification Notice and would appreciate an update on the status of the relocations. Your consideration of this matter is appreciated. Should you have any questions or need any additional information, please advise. Sincerely, Suza~,~aylor CIP CbSrdinator Engineering Department Direct: 972-304-7019 Fax: 972-304-3570 E-mail: sta¥1or~ci.coppell.tx.us 2S5 PARKWAY ~ P.O BOX 9478 ~{ COPPELL TX 750t 9 ~ TEL 9?2/462 0022 ~ FAX 972/304 3673 T H E~ C: ~ T Y 0 F COPPELL October 3, 2005 Ms. Jeanne Hooker Atmos Energy 14032 Distribution Way Farmers Branch, TX 75234 W. Sandy Lake Road ST 99-02 A Utility Relocation Status Dear Ms. Hooker: This letter is a follow-up to the city's August 23, 2005 utility meeting regarding upcoming construction projects. The W. Sandy Lake Road project is scheduled to advertise in November 2005 with an anticipated construction start in January 2006. The right-of-way acquisition is complete and all conflicting utilities need to be relocated and/or adjusted prior to the construction start date. Utility companies are required to submit a Right-of-Way Use Permit along with three copies of the relocation plans to the Engineering Department for approval prior to starting the relocations. It is our understanding that Atmos Energy has facilities within the project limits that will need to be relocated. We have not received any relocation plans or any updates since the utility meeting and would appreciate an update on the submittal of relocation plans and the estimated start and completion dates of the relocations. Your consideration of this matter is appreciated. Should you have any questions or need any additional information, please advise. Sincerely, Suza~ 3~aylor CIP Co6rdinator Engineering Department Direct: 972-304-7019 Fax: 972-304-3570 E-mail: stavlor@ci.coppell.tx.us October 3, 2005 Mr. Warren Fyffe Construction Coordinator Comcast Cable 1565 Chenault Street Dallas, TX 75228 W. Sandy Lake Road ST 99-02 A Utility Relocation Status Dear Mr. Fyffe: This letter is a follow-up to the city's August 23, 2005 utility meeting regarding upcoming construction projects. The W. Sandy Lake Road project is scheduled to advertise in November 2005 with an anticipated construction start in January 2006. The right-of-way acquisition is complete and all conflicting utilities need to be relocated and/or adjusted prior to the construction start date. Utility companies are required to submit a Right-of-Way Use Permit along with three copies of the relocation plans to the Engineering Department for approval prior to starting the relocations. It is our understanding that Comcast has facilities within the project limits that will need to be relocated. We have not received any relocation plans or any updates since the utility meeting and would appreciate an update on the submittal of relocation plans and the estimated start and completion dates of the relocations. Your consideration of this matter is appreciated. Should you have any questions or need any additional information, please advise. Sincerely, Suz '.a~'~'aylor CIP Odordinator Engineering Department Direct: 972-304-7019 Fax: 972-304-3570 E-mail: sta¥1or(~,ci.coppell.tx.us 255 PARKWAY 1¥ p.O,BOX 9478 3t COPPELL TX 75019 ~i' TEl_ 972/462 0022 'k FAX 972/3(~4 3673 T H E - C I T Y · 0 F' COPPELL October 3, 2005 Mr. Bob Buchowski Time Warner Telecom 15303 Dallas Parkway, Suite 600 Addison, TX 75001 W. Sandy Lake Road ST 99-02 A Utility Relocation Status Dear Mr. Buchowski: This letter is a follow-up to the city's August 23, 2005 utility meeting regarding upcoming construction projects. The W. Sandy Lake Road project is scheduled to advertise in November 2005 with an anticipated construction start in January 2006. The right-of-way acquisition is complete and all conflicting utilities need to be relocated and/or adjusted prior to the construction start date. Utility companies are required to submit a Right-of-Way Use Permit along with three copies of the relocation plans to the Engineering Department for approval prior to starting the relocations. It is our understanding that Time Warner Telecom has facilities within the project limits that will need to be relocated. We have not received any relocation plans or any updates since the utility meeting and would appreciate an update on the submittal of relocation plans and the estimated start and completion dates of the relocations. Your consideration of this matter is appreciated. Should you have any questions or need any additional information, please advise. Sincerely, Suzafi, 'l~aylor CIP C~b6rdinator Engineering Department Direct: 972-304-7019 Fax: 972-304-3570 E-mail: sta¥1or~ci.coppell.tx.us 255 PARKWAY ~r pO.BOX 9478 lie ¢OPPELL TX 75019 lk' TEL 972/~16~' 0022 ~' FAX 972/3(~4 3673 COFPELL October 3, 2005 Mr. Jason Carr MCI 2477 Gateway Drive Irving, TX 75063 W. Sandy Lake Road ST 99-02 A Utility Relocation Status Dear Mr. Carr: This letter is a follow-up to the city's August 23, 2005 utility meeting regarding upcoming construction projects. The W. Sandy Lake Road project is scheduled to advertise in November 2005 with an anticipated construction start in January 2006. The right-of-way acquisition is complete and all conflicting utilities need to be relocated and/or adjusted prior to the construction start date. Utility companies are required to submit a Right-of-Way Use Permit along with three copies of the relocation plans to the Engineering Department for approval prior to starting the relocations. Please let us know either way, if MCI does or does not have facilities within the project limits that will need to be relocated. If there are utilities that need to be relocated, we would also appreciate an update on the submittal of relocation plans and the estimated start and completion dates o£the relocations. Your consideration of this matter is appreciated. Should you have any questions or need any additional information, please advise. Sincerely, Suz~n X[aylor CiP O-6)ordinator Engineering Department Direct: 972-304-7019 Fax: 972-304-3570 E-mail: stavlor(D~ci.coppelI.tx.us 25S PARKWAY ~{ p.O.BO){ 9478 1~ COPPELL TX 75019 I~ TEL 972/462 0022 ~ FAX 972/3(~4 3673