Carrick Addition-CS010803 T H E · C: I T Y · 0 F
COP[SELL
August 3, 2001
Charles Statues
Statues Consulting Incorporated
4025 Woodland Park Blvd. Suite 230
Arlington, Texas 76013
Cardck Addition Lot 1 & 2 Blk A
Fee Assessment Letter
Park Development Zone: Zone 2
Dear Mr. Stames:
Enclosed is a copy of the City of Coppell Development Fee Assessment table, along with
a copy of the Development Fee calculations for the referenced development.
Please make payment for the Impact Fees to the City of Coppell in the amount of
$3,040.00 and forward to the Engineering Department along with a copy of the Fee
Assessment table. This amount is a portion of the assessed fees that need to be paid prior
to filing the plat.
The additional fees for water and sewer taps, water meters, and utility inspection fees
need to be paid by separate check at the Public Works Service Center, 732 Deforest.
Meters will be ordered when these fees are paid.
If you have any questions, please contact me.
Sincerely,
Kenneth M. Griffin, P.E.
City Engineer
CC~
Jennifer Armstrong, Finance Director
Rhonda Brothers, Engineering Secretary
Glenn Hollowell, Assistant Director of Public Works
Oreg Jones, Chief Building Official
Gary Sims, Director of Leisure Services
DEVELOPMENT FEE WORKSHEET
~ROJECT: Carrick ,4ddition Lot 1 & 2 Blk.4
.~ATE: 8/3/2001
Water Impact Fee:
Domestic Meter(s):
Irrigation Meter(s):
Fireline Meter(s):
1 - 5/8 inch X 3/4 inch = 1 ESU's
0 = 0 ESU's
0 0 ESU's
0 = 0 ESU's
Total #: 1 ESU's @ $450.00 ea.
(100% due prior to Council approval of the final plat)
Water Tap Inspection Fee:
Total #: 1 Connections @ $50.00 ea.
(Single family due prior to issuance of building permit)
(All other developments due prior to issuance of meter)
Domestic Water Meter Fee:
Total #: 1 Domestic Meter(s) @ $26.57
(Single family due prior to issuance of building permit)
(All other developments due prior to issuance of meter)
Irrigation/Fireline Water Meter Fee:
-- Total #: 0 Irrigation Meter(s) @ $0.00
Total #: 0 Additional Irrigation Meter(s) @ $0.00
Total #: 0 Fireline Meter(s) @ $0.00
(100% due prior to issuance of water meters)
Domestic Water Meter Deposit Fee:
Total #: 1 Meter(s) @ $35.00 ea.
(100% due prior to issuance of water meters)
Irrigation/Fire Meter Deposit Fee:
Total #: 0 Meter(s) @ $30.00 ea.
(100% due prior to issuance of water meters)
Wastewater Impact Fee:
Total Domestic Meters ESU's:
$450.00 ea.
Wastewater Tap Inspection Fee:
Total #: 1 Connections @ $50.00 ea.
(100% due prior to issuance of building permit)
Utility Final Inspection Fee (All developments):
Total #: 1 Lots @ $50.00 ea.
(100% due prior to issuance of building permit)
ark Fee (For Residential Developments Only):
$450.00
$50.00
$26.57
$0.00
$0.00
$0.00
$35.00
$0.00
$450.00
$50.00
$50.00
Page 1
DEVELOPMENT FEE WORKSHEET
* Preliminary plat approved: After October 26, 1993
Park Development Zone:
1 Single-family @ $1,285.00 per lot
0 Multi-family @ $1,285.00 per unit
(50% paid prior to Council approval of final plat)
(50% paid at issuance of building permit)
Roadway Impact Fee:
(See attached fee calculations)
Street Lighting Fees:
Assessed for lighting in the City's right-of-way.
This fee cannot be assessed until after T.U. Electric submits
the lighting plan for the proposed development.
Once the plans are submitted, $292.80 per light will be assessed.
(100% due prior to final acceptance of development)
Zone 2
$1,285.00
$0.00
$855.00
Information not Available
Street Sign Fees:
Assessed for signage in the City's right-of-way.
(See attached fee calculations if applicable)
Information not Available
Construction Inspection Fees:
A copy of the development contract must be submitted for assessment.
The contracts should indicate the cost to construct the improvements
that are inspected by the Engineering Department.
(2% of development cost required for private improvements)
(4% of development cost required for public improvements)
Information not Available
Page 2
ROADWAY IMPACT FEE CALCULATIONS
PROJECT:
DATE:
Carrick Addition Lot 1 & 2 Blk A
8/3/2001
ROADWAY IMPACT FEE:
Service Area * 2
Category ** Residential
Land Use ** Sin~le-F~trnily Detached
No. Lots/Units 1
Developmem Units ** 1.00
Vehicle Miles per Development Unit ** 2.85
Fee per Vehicle Mile *** $300
Roadway Impact Fee due = (Development Units) x
(Vehicle Miles per Development Unit) x (Fee per Vehicle Mile) = $855.00
* (Figure 2 ~ Roadway Impact Fee Study)
** (Table 3 - Roadway Impact Fee Study)
*** (Schedule 2, Page 3 - Roadway Impact Fee Study)
I AMOUNTDUE: $855.00 I
DEVELOPMENT FEE TABLE
Project: Carrick Addition Lot I & 2 Blk ~4
Date: 8/3/2001
TOTAL AMOUNT DUE
FEES DUE PRIOR TO
COUNCIL
APPROVAL
Water Impact Fee $450.00 $450.00
(100% due prior to Council Approval)
Water Tap Inspection Fee $50.00
(100% due at Issuance of Water Meter)
Water Meter Fee (Domestic) $26.57
(100% due at Issuance of Water Meter)
Water Meter Fee (Irrigation/Fireline) $0.00
(100% due at Issuance of Water Meter)
Water Meter Deposit (Domestic) $35.00
(100% due at Issuance of Water Meter)
Irrigation/Fireline Meter Deposit $0.00
(100% due at Issuance of Water Meter)
Wastewater Impact Fee $450.00 $450.00
(100% due prior to Council Approval)
Wastewater Tap Inspection Fee $50.00
(100% due at Issuance of Building Permit)
Utility Final Inspection Fee $50.00
(100% due at Issuance of Building Permit)
Park Fee $1,285.00 $1,285.00
(100% due prior to Council Approval)
Roadway Impact Fee $855.00 $855.00
(100% due prior to Council Approval)
Street Light Fee Information not Available
(100% due prior to Acceptance of Project Il
Street Sign Fee Information not Available
(100% due prior to Acceptance of Project I[
Construction Inspection Fee Information not Available
TOTAL $3,251.57
TOTAL AMOUNT DUE PRIOR TO COUNCIL APPROVAL $3,040.00