Dear Mr. Horton:
The following is a list of deficient items that must be corrected prior
to issuance of City Acceptance Letter. As the deficient items are completed,
please notify appropriate department for verification.
Water Utilities
Street Department
Park Department
Fire Department
Developmental Inspection
Howard Pafford
Per Birdsall
Richard Diano
Troy Glidewell
Steven Morton
Water Utilities Department
1. All manholes and sanitary sewer line need to be flushed and cleaned.
2. 8" water in-line gate valve at 4 + 66.28 needs to be located.
3. There were several water and sewer services that we were not able to
locate, they are as follows:
1. BLOCK 1 - Lot 4 move (w) marker 2 feet south - Lot 1 no water or sewer
- Lot 8 no sewer
- Lot 9 raise meter box and no sewer
- Lot 10 sewer for this lot on Lot 11
- Lot 19 no sewer
- Lot 22 move (w) marker 2 feet east
2. BLOCK 2 - Lot 1 replace meter can - Lot 4 no sewer
- Lot 6 no sewer
- Lot 7 no sewer
- Lot 12 water for this lot on Lot 11
- Lot 13 no sewer
- Lot 14 move (w) marker 4 feet east
- Lot 15 raise meter can
- Lot 16 raise meter can
' ton'tinued:
- Lot 19 no sewer
- Lot 20 move (w) marker 2 feet west
- Lot 22 no water or sewer
3. BLOCK 3 - Lot 1 replace meter can and 2 water services - Lot 2 sewer and water are only 2 feet apart,
10 feet apart
- Lot 3 no sewer
on this lot
need to be
STREET DEPARTmeNT / PARK DEPARTMENT (combined)
1. Route and seal crack @ Cove and MacArthur in right turn
2. Letter of Irrigation Commitment
3. Lugs missing on all brick pavers
4. Clean up wall
5. Grade to drain all foot areas of wall
6. Route and seal curb cuts at expansion joints
7. Lot 6 repair lake wall
8. Route and seal cracks@ Bay Circle E. @ Parkway between brick and curb
9. Route and seal cracks @ Bay Circle @ culdesac
lB Remove form in manhole in alley,~compact
FIRE DEPARTMENT
Oil all fire hydrants.
DEVELOPMENTAL INSPECTION
1. One yearmaintenance bends
2. As-Built drawings 2-mylar 2 blue lines
3. Lien Release letters from contractors
Thank you for your cooperation in this matter. If you have any questions
or comments, please feel free to contact me at 462-8495.
Steven M. Morton~ ............
Chief Develo~tal Inspector
SMM/bb
continued:
cc: Steve Goram, Director of Public Works
Howard Pafford, Water Utilities Foreman
Per Birdsall, Streets Foreman
Richard Diano, Parks Foreman
Troy Glidewell, Fire Marshall
COPPELL PUBLIC WORKS
~F~MORANDUM
July 14, 1988
Steven M. Morton, Chief Develoi~mental I~pe~or
Howard Pafford, Water Utilities Foreman~
Channel Pointe Walk Through
Steve, listed below are the items we found in our walk that need to be corrected:
1. All manholes and sanitary sewer line need to be flushed and cleaned.
2. 8" water in-line gate valve at 4 + 66.28 needs to be located.
There were several water and sewer services that we were not able to locate,
they are as follows:
1. BLOCK 1 - Lot 4 move (w) marker 2 feet south
- Lot 1 no water or sewer
- Lot 8 no sewer
- Lot 9 raise meter box and no sewer
- Lot 10 sewer for this lot on Lot 11
- Lot 19 no sewer
- Lot 22 move (w) marker 2 feet east
2. BLOCK 2 - Lot 1 replace meter can - Lot 4 no sewer
- Lot 6 no sewer
- Lot 7 no sewer
- Lot 12 water for this lot on Lot 11
- Lot 13 no sewer
- Lot 14 move (w) market 4 feet east
- Lot 15 raise meter can
- Lot 16 raise meter can
- Lot 19 no sewer
- Lot 20 move (w) marker 2 feet west
- Lot 22 no water or sewer
3. BLOCK 3 - Lot 1 replace meter can and 2 water services on this lot - Lot 2 sewer and water are only 2 feet apart need to be 10 feet
- Lot 3 no sewer
Steve, I would say overall that they should make sure each lot has water/wastewater
services and they are properly marked before staff does final walk through.
If you have any questions regarding this matter, please advise.
HLP/bb
cc: Steve Goram