Loading...
CF TownC P/C-CS 970327DATE: TO: FROM: RE: "~ COPPELL ENGINEERING March 27, 1997 Larry Davis UTILITIES DIVISION MEMORANDUM Brent Adams, Street Division Walk thru for Justice Center A walk-thru on the above referenced project was conducted on and the items below were found to be deficient. 1. 2. 10. i1. 12. 13. 14. March 27, 1997 North Drive Approaches & Parking North Drive Approach, North Side of Drive Approach- Seal Curb return. 10 to 12 foot to the South Rout & Seal Random Crack Center of Approach- Rout & Seal Random crack that is running Parallel to street about 15' foot off of street. South of Drive Approach- Remove concrete spill aim repair curb same location. North Parking - Rout & Seal Random crack between third parking spaces from the North off of center line on parking lot. North Parking - Install additional parking bumper along sidewalk area on East side of parking lot. Also seal between parking lot & sidewalk same area ADA area. Rout & Seal Curb & Drive area on South side of center drive 18 feet east of approach brake. Repair sidewalk in the ADA Ramp Center Dr. N. Side of Dr. Remove forms main entrance by Flag Poles. South Drive approach & Parking sidewalk Sidewalk N. side of drive way approach seal ADA ramp. South side repair sidewalk. Rout & Seal random crack at Chain link fenced area gate back of building. Rout & Seal random crack at planter island first parking space by side garage door south east side. Please ensure that these items get taken care of and if you have any questions, please give me a call. MMC/dg STATUS ON WORK 0g;i..I)ERS Employee_ Phone #