Coppell BC3 Con-CS000914 MEMORANDUM
FROM THE
DEPARTMENT OF PUBLIC WORKS
To.'
From:
Date:
RE:
LannyAllison, Construction Inspector Engineering
Larry Morton, Streets Division Public Works
September 14, 2000
Walk-thru Coppell Business Center HI Lots 1 & 2 Block C
PAVING
1. Need to pull all backer rods out of joints in approaches including curb joints and clean
them and ref'dl with silicone sealer. There is no sealer in them at this time.
DRAINAGE
1. Cannot inspect until storm drain inlet boxes on Wrangler are cleaned out.
CITY OF COPPELL PUBLIC WORKS DEPARTMENT
MESSAGE
CONF I RMAT I ON
IDzCITY OF COPPELL
DATE
09/14
S,R-TIME DISTANT STATION ID MODE PAGES
00~21" CITY OF COPPELL CALLING 01
RESULT
OK 0000
September 12, 2000
Kyle Brarnlett
Lincoln Property Co.
3300 Lincoln Plaza
500 N. Akard
Dallas, Texas 75201-3394
RE: Coppell Business Center III, Lots l&2, Block C
Dear Mr. Bramlett:
Please be advised that a walk-through has been scheduled for Thursday, September 14, 2000 at
9:00 a.m. for the water, sanitary sewer, paving and drainage facilities in the referenced project.
Please ensure that all facilities are clean and accessible at that time and that contractor's
representatives are present to assist with the inspection.
Your cooperation in this effort is greatly appreciated. If you should have any questions, please
call 972-304-7090 at your earliest convenience.
Sincerely, ·
Lanny Allison
Construction Inspector
CC:
Chris Butler, Butler Construction (fax 817-267-1902)
James Corer, TriDal (fax 817-481-8195)
Mike Martin, Assistant City Engineer
DeN Ingram, Engineering Secretary
Glenn Hollowell, Director of Public Works
Greg Jones, Chief Building Official
Travis Crump, Fire Marshal
T H E C I T Y · 0 F
September 12, 2000
Kyle Bramlett
Lincoln Property Co.
3300 Lincoln Plaza
500 N. Akard
Dallas, Texas 75201-3394
RE: Coppell Business Center III, Lots l&2, Block
Final Walk-thru ~.~)~0~.0.~ ~~
Dear Mr. Bramlett:
Please be advised that a wall-through has been scheduled for Thursday, September 14, 2000 at
9:00 a.m. for the water, sanitary sewer, paving and drainage facilities in the referenced project.
Please ensure that all facilities are clean and accessible at that time and that contractor's
representatives are present to assist with the inspection.
Your cooperation in this effort is greatly appreciated. If you should have any questions, please
call 972-304-7090 at your earliest convenience.
Sincerely, ·
Lanny Allison
Construction Inspector
CC:
Chris Butler, Butler Construction (fax 817-267-1902)
James Cofer, TriDal (fax 817-481-8195)
Mike Martin, Assistant City Engineer
Debi Ingrain, Engineering Secretary
Greg Jones, Chief Building Official
Travis Cramp, Fire Marshal