January 17, 1990
TO:
FROM:
RE:
Steve Goram, Director of Public Works
Russell Doyle~y Engineer
Connell Skaggs Drainage Contract (Tickler 1/19/90)
Jim Koch indicates that the channel to be lined would be
$80,000.00 ($20,000.00 excavation, $60,000.00 concrete).
Jim Koch will send me more information via the design drawings
of the 10 x 8 box for the entire length. Also, neither Mark
Connell nor Jim Koch knows what's meant in the agreement by
the "Engineering Study".
Amy Crowley indicated Connell contributed $44,121.72 toward
the Sandy Lake and Denton Tap Roads intersections and they do
not know if Connell would get credit for that amount against
paving assessments on either street.
Requested meeting is set for 10:30 a.m. on Friday, January 26,
1990.