Loading...
Cottonwood-CS 920214COPPELL PUBLIC WORKS DATEs TO: FROM: RE: FebruarH 14; 1992 Steven G. Goram, Director of Public Works Rey Gonzales, Streets Superintendent ~ Cottonwood Drive Slurry Seal Program (Tickler 2/14/92) As per our conversation this morning I have contacted Mike Sharp's office and have advised him that we would like for Austin Paving to begin work as soon as possible. He is going to contact them and set it up for start up on February 24, 1992. I told him that we want West Bethel done first. He said that his crews would be pulling the shoulders prior to the overlay and placing the R.A.P. approximately 2 weeks after the overlays are completed to allow for cure time of the new asphalt. He did say that the road edge will be beveled to provide for less of a drop off. Next status 2/24/92. RG/bc STASPOL.RG