March 4, 1994 /\( /
Larry Davis, Construction Inspector
Howard L. Pafford, Utilities Superintenden
Final Walk-Through of Creek'view II Subdivisior~
Staff performed a final walk-through of the above referenced subdivision yesterday morning.
The following is a list of deficiencies found on this project:
o
Meter can run over and crushed at Lot 1. Replace meter can and repair or replace
setter and copper if damaged.
All meter services a testable double check device in a separate meter can as required
for a commercial development.
Lot 3 - There is no water service, end valve, or 2" blow off. Has water line been
installed?
8" sewer tie in at Sta. 0+0.0 - Pipe needs to be grouted and invert fixed to allow
proper drainage of line into existing sewer line. Manhole connection should have
been core drilled. Due to the fact that the manhole was broken out, a concrete sealer
is required on the interior and exterior or' the connection and the exterior pipe must be
totally encased in concrete one foot around the pipe, three feet out.
Manhole at Sra. 2+73.12 - Unable to locate.
Both installed manholes need rainpans according to City specifications.
Sewer lines need to be videoed and cleaned.
Tract I on north side of Bethel Road - Water service and sewer service need
uncovered and sewer service needs to show proof of installation (meter with separate
donble check).
9. Fire hydrant street indicator or blue dot placed on street.
10. All manholes, meter can valves need to be staked to mark their locations,
Based on staff's findings, this walk-through should have been conducted at a much earlier
date; however, no formal notice of a scheduled walk-through was received by this division.
I will also mention that based on the procedures used to perform these installations, the
construction inspection process of this project should have been monitored more closely.
Please notify the utility contractor of the deficiencies and notify this division when a follow-
up walk-through is necessary. I would expect these deficiencies to be corrected in a timely
manner due to the fact that construction is already taking place on one of these lots.
HLWdm
WALKTHRU.HLP/CREEKVU