ST8201-CS 891206Date: To: From: Re: MEMORANDUM December 6, 1989 Steve Gor~ John C. Karlsruher, P.E. Weekly Status Report 11/25/89 Sunday - clear, mild - no work 11/27/8g Monday (57'-7g°) clear, mild, ~M humidity g3% North Project L. H. Lacy Co. - Glenn Milsap, 12 men, slip form paver - Poured 22 1/2' width right of centerline eta. 166+58 to 170+64 ± from 7:15 AM to 3:00 PM. Four concrete cylinders taken Sra. 168+75 - R & M Concrete Co. Ticket #042939 accum, total: 171 C.Y. 5 sack mix. Discussed procedure on curing of the slab i.e., maintaining temperature for a minimum of 19 hours, as per T.H.D. specs, with Scott Belch and Glenn Milsap. Poly sheeting was discussed and approved, as long as wind did not flow between top of slab and bottom of plastic. Cold front scheduled to penetrate north Texas in the late evening with early morning temperatures to be in the middle to upper 30's. South Project L. H. Lacy Co. - Brent, 8 men - Forming left turn lane and tying steel at Meadow Creek-Denton Tap Road and at Sta. 100+00. CoDeland Enterprise - Gary Davis, 8 men - Pouring concrete foundation shafts for metal guard rail left of centerline Sta. 125+00 to Sta. 120+00 from 9:15 AM to 11:45 AM. Gifford-Hill Concrete Co. 5-sack mix #GHS-79. Brooks-Maltbv. Inc. - 3 men - Working on 2" rigid galvanized pipe on NW corner of Grapevine Creek Bridge, due to being in conflict with metal guard rail posts. Met with Bill Brooks at 2:00 PM and discussed 2" PVC conduit conflict with Texas Utilities' proposed light foundation on north side median nose Sta. 161+00 ±. Texas Utilities - Pete, 2 men - Installing 2" sweeps off of existing conduit runs for street lights at Sta. 130+50 to Sta. 125+57. 11/28/89 ~uesd&¥ (~8'-49') X]( w~ e~ll £&otor 22'~ 48% h~i~it¥ at 3:00 PM No~th ~ro~eot ~ - Glenn Milsap, 12 men, i screed paver - Pouring inside 11 1/2' width and left turn lane sra. 166+58 to 170+64 from 1:30 PM to 6:30 PM with a 6-sack mix from R & M Concrete Co. Note: Did not install poly sheeting on top of 22 1/2' width concrete pavement as previously discussed for maintaining proper curing temperatures (11/27/89 production)- ~ - 3 men - Remedial repairs on brick pavers on SW intersection of Parkway Blvd. at Denton Tap Road and x-walks. Brooks-Maltbv. Inc. - Installing bridge lighting galvanized rigid pipe on SW corner of Cottonwood Creek Bridge. gitv of CODDell - Ted, 1 man, 1 backhoe - Repaired brass corporation in 8" PVC main right of centerline Sta. 196+30 ~. south Project ~ - Glenn Milsap, 12 men, i screed - Poured left turn lane (add-on) at Denton Tap Road-Meadow Creek Sra. 117+50 ± from 7:45 AM to 10:20 AM. Poured left turn lane (add-on) at Denton Tap Road Sta. 100+00 from 10:30 AM to 1:00 PM. Mobilized to north project. Copeland EnterDris~ - Gary Davis, 6 men - Working on metal guard rail on south side of Grapevine Creek Bridge, in median island and on NW section from 120+00 to 117+50 ~. General clean-up from 125+00 to 120+00 left of centerline. Te s t'lities - Pete, 2 men - Installing 2" sweeps for proposed street light foundations in median sta. 125+57 to sta. 120+00. 11/29/89 Wednesday (37°-51°) XM cold, PM partly oloudy, 28% humidity North Projeot · . c co. - 2 men, 1 saw - Sawing controlled d~mmy joints in concrete paving right of centerline Sta. 166+58 to 170+24 (inside 11.5' width and left turn lane) from 11:00 AM to 3:00 PM. Concrete slab was covered with plastic last night and was removed at 9:00 AM this morning· south Project ~ - i man, 1 saw - sawing controlled d~my joints in concrete pavement for Meadow Creek Drive left turn lane and then sawed left turn lane right of centerline Sta. 100+00. Could not saw yesterday, as stated by Glenn Milsap, due to being too green (not sufficiently hardened). Plastic was placed on top of concrete slabs last night at approx. 7:00 PM. Brooks-Maltbv. Inc. - 3 men - Working on PVC conduits within median island Sta. 170+64 to 166+58. CoDeland Enterprise - 6 men - Erecting metal guard rail left of centerline Sta. 198+00 to 202+00. south ProJeot L. H. Lacy Co. - Mike, 4 men, clean-up crew - Construction debris removal for 2-1eft turn lanes Sta. 117+00 and Sta. 100+00. Brooks-Maltbv. Inc. - 3 men - Working on PVC conduits within median island Sta. 162+75 to Sta. 163+75. CoDeland Enterurise - 6 men - General clean-up at median island guard rail Sta. 114+00 and left of centerline Sta. 117+50 to 120+00. Texas Utilities - Pete, 2 men - Working on street light foundations.