ST8201-CS 891018COPPEIJ~ PUBLIC WORKS
MEMORANDUM
DATE=
October 18, 1989
FROM:
RE=
Tap
Alan Ratliff, City Manager
Steve Goram, ,D~'~ctor of Public Works
Russell Doyl~ty Engineer
Left-Turn Lane/Springs of Coppell Addition/BFT/Denton
Road from Beltline to Sandy Lake Road
As we discussed, per your phone inquiry to Russell R. Doyle,
P.E. City Engineer, subject left turn-lane will be built as a part
of the Denton Tap Road C.I.P. project. Per John Karlsruhrer, the
left-turn lane will be installed within the next two (2) months by
Lacy Company when they place the remaining pavement at Denton Tap
and Sandy Lake Roads. As you will recall the placement of that
pavement was held up due to the Dallas Water utilities transmission
line adjustment.
The other left-turn lane relating to subject Addition was
already placed on the Denton Tap C.I.P. project for the Bethel Road
intersection.
Please let us know if you need any further information on this
matter. Thank you.
SGG/RRD/SD/pd/file
xc: John Karlsruhrer