TexasBank 2R-CS051026October 26, 2005
Chris Ripke
Workman Construction
Fax:,~.°'"~':',,o,,. ,~,,,,~,'°~° q?g/7qr-7/4g
RE: TexasBank Addition, Lot 2R Block A (Creme de la Creme)
Dear Mr. Ripke:
Please be advised that a walk-through inspection is scheduled for Thursday, October 27, 2005 at
1:30 p.m. for the water, sanitary sewer, paving and drainage facilities in the referenced project.
Please ensure that all facilities are clean and accessible at that time and that contractor's
representatives are present to assist with the inspection. Your cooperation in this effort is greatly
appreciated. If you should have any questions, please call 972-304-7090 at your earliest
convenience.
Sincerely,
Rick O' Dell
Construction Inspector
Office Phone: (972) 304-7090
Fax: (972) 304-3570
CC:
Keith R. Marvin, P.E., Asst. City Engineer
Glenn Hollowell, P.E., Asst. Director of Public Works
Greg Jones, Chief Building Official
Tim Oates, Fire Marshal
PARKWAY ~1~ p.O,BOX 9478 ~ COPPELL tX 75019 ~ TeL 972/462 0022 ~ fAX 972/30d 3673