MA 9601-CS 890413COPPELL PUBLIC WORKS
MEMORANDUM
April 13, 1989
TO: Steve Goram, Director of Public Works
FROM: Per Birdsall, Street Foreman'
RE: Major Projects
SUBJECT:Asphalt Overlays - Deforest. Thweatt,
Tickler 4/11/89
Bethel, Southwestern
Contingent of the County Commissioner Court's approval of the court
order, which would allow the County to perform the overlays proposed,
the County should begin work on April 19th, 1989. Mike Sharp has
indicated that the order of overlays (Deforest, Thweatt, Bethel,
Southwestern) can be implemented. Deforest Road has no problem
with beginning, Thweatt Rd. (at Royal Ln. Extension) will be off
of the roadside by the 19th according to Steve Morton, Bethel Rd.
has two projects that call for trucks (Bethel box culvert and the
Post Office) primarily concrete, Southwestern Blvd. will have the
waterline coming through in May (?).
PHB/bb
cc: Ail asphalt overlay major projects