Loading...
MA 9601-CS 880510INC. i~y 10, 1988 CO N S U LTiDJIi-EqN :7.EE R S TO: Alan D. Ratliff, City of Coppell Monthly Report City Manager ~ [~].].o%~ng monthly report reflects the current status of each ~,~ che cuFrent active projects that we are working on for the ~¥ of coppell. We have prepared the information in executive ~ ~n~ma~y fo~m for your convenience. We will be happy to expand on ~h,~ information provided for any particular project should you so ~REET PROJECTS 1.. Belt Line Road (South) Construction began March 2, 1987. Contract completion date August 22, 1988. As of April 30, 1988: 63% work completed versus 78% contract time. hdjusued contract amount to date (with Change Orders) $5,657,864.91. Contractor currently completely storm sewer. Phase III paving of two northbound lanes (Sanders Loop northward) completed. Cowboy Drive intersection paving completed. Cowboy Drive intersection shall be re-opened to traffic May ]4, 1988. ~ Pethel School Road Construction began September 1, 1987. Contract completion date June 26, 1988. O~iginal contract amount $618,526.94. As of April 30, 1988: 89% work completed contract time. Paving on south half of roadway is completed. currently performing clean-up, backfilling open to two-way traffic approx. May 27, 1988. versus 80% Contractor parkways, etc. 171113 Preston Road · Suite 100 · LB 118 · Dallas, Texas 75248 · Phone 214/248-4900 _~!*%~t o!!_ Tap Road Contracts for both segments awarded April 26, 1988 to L.H. ~cy Co. (total amount $5,191,943.03). Belt Line to Sandy Lake segment - estimated construction st~]-t June, 1988; complete June, 1989 (Contract amount $3,38H,580.00) . Sandy Lake to Denton Creek segment - estimated construction start June, 1988; complete June, 1989 (Contract amount $1,803,363.03). Total project cost including traffic signals, street lights~ landscaping, and RxR crossing etc. is approximately $7,200,000.00. Agreements still pending with Conoco, Explorer, and St. Louis Southwestern Railroad. Belt Line Road {E/W) L~--dasign of paving and drainage improvements for segment - ~.~acArthur to West overflow swale is 40% complete. Dallas County would like to bid this portion of Belt Line Road with Carrollton's portion. Due to R.O.W. problems R x R, the county is currently re- designing the Carrollton portion of the project. Anticipated completion date for the re-design and subsequent bidding and construction is unknown at this time. Belt Line (E-W) relocation west of MacArthur Awaiting final execution of City/Developer agreement. %~ATER PROJECTS 5. 24" Cross-town Water Line Design 82% complete. Anticipate completion of design end of June, 1988. Design in progress for segment along MacArthur and Sandy Lake to new pump station site. Still awaiting City of Dallas design and route approval. Estimated construction cost $1,500,000.00. Ground Storaqe Tank Design 85% complete. Anticipate bidding in late May 1988. Pump Station Design 25% complete. Will present revised tank is bid. bid and construction schedules after ,~YflCELI~ANEOUS PROJECTS ~adow_~idqe Drainaqe problem No change in status since.last report. Belt Line Traffic Signals Design and specs, completed. Bid: June 2, 1988. Scope: Permanent signals for Cowboy/Belt Tap/Southwestern/Belt Line intersections. Estimated construction cost $175,000.00. Line 121 By-Pass No activity this period. Cotton Road Name Chanqe No luther participation by Ginn, Inc. on, this requested. City Attorney pursuing annexing south half of R.O.W; time. ~.~ame change to be pursued by City staff thereafter east/west segment, west of IH635. and Denton project at this for the Sub-Division Ordinance Revisions Preliminary draft complete and submitted to City r{anager/staff for review. Submitted work order form to City for authorization of this ~roject for our records. '}3. Postal Facility Received change order mid-April. Hope to have agreement between 1988 to present to Council. i. 4. P & Z City/Minyards in May/June, Working with staff on as-needed basis. Current projects are: Northlake Industrial Tract, Riverchase Clubhouse Addition, Gateway Park at Coppell, 'galley Ranch Plaza (Pad A - Exxon), Meadows (Section 6), Fairway Drive, Century Park (Magnolia), Exxon (Sandy Lake Crossing), Channel Pointe. '~.5. MacArthur Blvd./Sandy Lake Intersection No change in status. Provided cost estimate at February 9, 1988 Council meeting for temporary signals (ie., poles and span wires vs. permanent mast arms). Currently awaiting City's authorization to proceed with design, bid and construction. Sandy Lake Rd./Moore Rd. Intersection No change in status. Improvements needed to install loop detectors and protected left-turn at this intersection per City's request. Prepared cost estimate and presented at February 9, 1988 Council meeting. Plan is to include in bid package with Sandy Lake/MacArthur signa].s. Will proceed with design, bid and construction upon City's authorization of project. Elevated Water Storage Tank No further action requested of Ginn, Inc. at this time. City staff pursuing bids. DeForest Road Pavinq Improvements No change in status. Cost presented at February 9, 1988 Council meeting. Currently awaiting City's authorization to proceed with this project. '~9. Floodplain Administrator Working with City on as-needed basis. Thompson Tract Access to TRA System Completed. Thompson's content. Larry Jackson "hold harmless" currently reviewing Johnny instrument for proper form and Whispering Hill Drainage Study No change in status. Cost presented to Council February 9, 1988. CurrenEly awaiting City's authorization to proceed. Mapping Same status as above. Parkway Boulevard Paving Same status as above. Samuel Boulevard paving Same status as above. you for the opportunity to work with the City of Coppell on ~nd £uture projects. ~espect fully submitted, Wayne Gi~,~P. E. ~'lty Engineer