MA 9601-CS 871118MEMO
Date:
To:
From:
Subject:
November 18, 1987
H. Wayne Ginn
Butch Ellison
~D~Forest Rd. Improvements Approx. 800'x22' wide
(informatioh received via phone from Mike Sharp)
WORK TO BE DONE:
1. Clean ditches and remove trees on north and south side of
DeForest/Rd. from MacArthur Blvd. to east end of Service
Center Drive.
Install 32' of 18" round corrugated pipe (Mike would prefer
using oval pipe 22" x 13") to facilitate drainage under and
across road at existing sag point.
Remove existing base to accommodate 6" of CTB and 2" of hot
mix.
4. Mat removed to be re-used in raising road surface at sag
with approximately 150' transition from centerline of drain
pipe east and west.
Est. cost
Time to do
Can start
$21,000.00
5 working days
next week
Additional costs:
If city wants to -add 2" ~i-~h- topping on existing road surface
from Service Center Drive east to end of DeForest add $16,500.00.
Note: Mike Sharp said UVALDE will do this work.