MA 9601-CS 871118MEMO Date: To: From: Subject: November 18, 1987 H. Wayne Ginn Butch Ellison ~D~Forest Rd. Improvements Approx. 800'x22' wide (informatioh received via phone from Mike Sharp) WORK TO BE DONE: 1. Clean ditches and remove trees on north and south side of DeForest/Rd. from MacArthur Blvd. to east end of Service Center Drive. Install 32' of 18" round corrugated pipe (Mike would prefer using oval pipe 22" x 13") to facilitate drainage under and across road at existing sag point. Remove existing base to accommodate 6" of CTB and 2" of hot mix. 4. Mat removed to be re-used in raising road surface at sag with approximately 150' transition from centerline of drain pipe east and west. Est. cost Time to do Can start $21,000.00 5 working days next week Additional costs: If city wants to -add 2" ~i-~h- topping on existing road surface from Service Center Drive east to end of DeForest add $16,500.00. Note: Mike Sharp said UVALDE will do this work.