Creekview North-CS 881107 (2)COPPELL PUBLIC ~ORKS
November 7, 1988
TO: Taryon Bowman, Planning & Zoning Coordinator
FROM: Richard Diano, Park Foreman~
RE: Fee Assessments - P~rk
PROJECTS: Shadow Ridge Phase III, Creekview
Riverchase Phase I
North, Fairways @
Listed below are the fees assessed for the above referenced projects:
Shadow Ridge Phase III
Park Fee of $150.00 per unit x 9 units = $1,350.00
(50% due @ submission of.final plat) =. $675.00
(50% due @ issuing of building permits) = $675.00
Creekview North
Park Fee of $150.00 per unit x 4 units
(50% due @ submission of final plat) =
(50% due @ issuing of building permits)
$600.00
$300.OO
:$300.00
Fairways @ Riverchase Phase I
Park
Fee of $150.00 per unit x 84 units = $12,600 00
(50% due @ submission of final plat) = $6,300.00
(50% due @ issuing of building permitg)=$6,300.00
RED/sm
cc: Steve GOram, Director of Public Works