ST8201-CS 891019Date=
To:
From:
Re:
, . , .
10/8/89, Sunday, clear, mild
North and south Projects - Contractors did not work
10/9/89. Monday (54'-84°) - cool, clear, s.n~y
North Project
City of Dallas Water Utilities - same men and equipment - Located
leak on Friday, 10/6/89. Bell and spigot joint on 1st and 2nd
joint (south end) leaking. Gilford-Hill American Pipe Co. had 2
certified pipe welders working at this location. Repairs
completed and line retested in the afternoon. Start backfill.
- No work, as with their sub-contractors.
~ooks-Maltb~. Inc. - Did not work
Jim Bowman Const. Co. - James Long, 7 men, 1 crane - Installing
forms on east bridge, west side, north 1/2 railing. Inspection
from 2:00 PM to 2:45 PM. Concrete placed at 4:00 PM to 6:30 PM.
T. X.I. concrete with plasticizer.
~ Co. - Steve, 6 men, 2 grinders, i loader - Remedial
work on Northwest countersink on Bethel School Road and northeast
countersink on Bethel School Road. Grinding for the required 4"
depths.
Dave Carlton - 3 men, 1 backhoe - Verifying water valves in
concrete pavement and locating sanitary sewer manholes in slopes
for required adjustments.
Eaqle Const. Co. - Doug, 4 men - Poured remainder of northeast
radius fillet on Bethel School Road-Denton Tap Road. Poured
remaining block-outs around water valves for F.H.'s. Making
grade on southeast wheel chair ramp at Bethel School Road-Denton
Tap Road.
10/10/89 Tuesday (56'-87', 60% humidity in AM) - oool, sunny, mil~
North Project
city of Dallas Water Utilities - Compaction Equipment (vibra-
plate) used yesterday, for trench backfill, has been discarded.
John Karlsruher, P.E. made phone call to Calvin Winchester (City
of Dallas) and informed him on methods used for compaction
yesterday. New compaction equipment being used today. Adding
water to soils for obtaining the required moisture for density
requirements. Pulled bacteriological water samples in the
morning and submitted for analysis.
South ProJeot
Brooks-Maltbv. Inc. - 3 laborers, 1 backhoe - Installing 2-3" PVC
conduits omitted in the NE wheel chair ramp at Bethel School
Road/Denton Tap. Installing pull boxes in same area, at both
North and South corners of Bethel School Road, east side.
Lectric Safety Lites - Marvin, 2 men Button layout on
southbound lanes from Sandy Lake/Denton Tap to Meadow Creed Road
in the morning. Installed 4" skip lane buttons on southbound
lane from Braewood dRive to Meadow Creek Road.
~ Co. - Steve, 6 men, 2 grinders, I loader - Grinding
southeast countersink of Bethel School Road. Compacting soils
for brick wheel chair ramps at both NE and SE corners of Bethel
School Road.
Jim Bowman Construction Co. - James Long, 7 men, 1 crane -
Recycling rail forms from yesterday's pour to the west bridge,
east side, north 1/2.
10/X~/89, Wednesday (55°-95°) - olear, sunn~, warm
North Project
City of Dallas Water Utilities - same men and equipment - Trench
backfill (density control) on the lowered 100 ft. length.
~ Co. - Not working
South Project
Eaale Construction - Doug, 6 laborers - Forming wheel chair ramps
on SE radius of both Braewood and Bethel School Road. Inspection
at 1:45 PM. Concrete poured from 4:00 to 5:30 PM.
Brooks-Maltbv. Inc. - 3 laborers, 1 backhoe - Re-working 2-3" PVC
within NE wheel chair ramp and 1-3" PVC within SE wheel chair
ramp at Bethel School Road. Wrong alignment location and shallow
depths. Time: 8:30 AM to 10:30 AM.
S - t - 3 men, bore operation - Boring 2-3" PVC for both
NE and NW section at Bethel School Road omitted prior to paving.
Bored an 8" diameter hole at both locations. Pressure grouting
voids will be required.
c . - Steve, 6 men, I loader, 2 grinders, i small
sheepsfoot roller - Compacting soils for NE wheel chair ramp on
Bethel School Road after remedial work on 2-3" PVC installation.
Grinding brick countersinks for crossing on southbound lane of
Bethel School Road/Denton Tap.
~ - 3 men, i small backhoe - Manhole excavation for
adjustment and water valve locate.
Lectric Safety Lites - Marvin, 2 men - Install 4" skip lane
buttons from Meadow Creek to Dairy Queen on southbound lanes.
Install 4" skip lane buttons from Sandy Lake Road to Braewood in
the afternoon (southbound lanes).
Jim Bowman Construction Co. - James Long, 7 men, i crane -
Installing rail forms on west bridge, east side, north 1/2.
Miscellaneous Items - Transition from 3 lanes into 1 lane from
Sta. 145+00 ± to Bethel School Road intersection (southbound
lanes) to accommodate installation of brick pavers.
10/12/89, Thursday (65°-92') - clear, s.n,y
North Project
city of Dallas Water Utilities - same men and equipment
backfill, density control·
Trench
L. . c o. - Did not work
South Project
Eaale Construction Co. - Did not mobilize today.
Jim Bowman Construction Co. - James Long, 7 men, i crane -
Installing rail forms for west bridge, east side, north 1/2.
Inspection at 4:00 PM to 4:30 PM. Concrete placed from 5:15 PM
to 7:00 PM. Finish work on concrete at 7:30 PM. Two men re-
tieing rail steel for west bridge, west side, north 1/2 section·
~uma-Stone - 8 men - Installation of brick pavers at both north
and south 2 inside lanes of southbound traffic at Denton Tap
Road/Bethel School Road. Installation of NW 1/2 of Bethel School
Road also. Note: Flagmen not present during street closures.
Traffic not knowing what is happening. Contractor tried to
depart from project at 5:00 PM without opening Bethel School Road
(west). Construction phasing will not allow for 2-way traffic
onto Bethel School Road (west). Called Scott Balch at main
office and advised him to control his sub-contractor and open
roadway ASAP. L. H. Lacy personnel flagged traffic from 5:20 PM
to 6:30 PM. Opened Bethel School Road, west side, at 6:30 PM,
prior to initial lock-up of brick. Brick not sanded nor
compacted prior to opening traffic. Out of specifications. Bad
cuts on brick pavers.
South ProJeot
C . - Steve, 6 men, 2 grinders, i loader - Remedial
work on brick countersinks at north and south crosswalks on
Denton Tap Road southbound inside lanes at Bethel Road
intersection.
Dav~ Carlton - 3 men - Three manhole adjustments and water valve
2'x2~ concrete pads.
~rooks-Maltbv. Inc. - 3 laborers, I backhoe - Installing sweeps
and pull boxes for PVC conduits from Bethel School Road to Meadow
Creek. Four foot long void below brick median cap noses on
either side of Denton Tap Road/Bethel School Road. Informed
Scott Balch, again, regarding the excavation under roadways and
concrete noses.
Lectric Safety Lites - Marvin, 2 men - Installation of left turn
lane buttons from VanBebber to Minyards (southbound lane) and
from Meadow Creek to Dairy Queen (southbound lane).
Miscellaneous Items - 1.) Called Tim Brancheau with T.U.
Electric regarding power poles and down guy wires in the proposed
wheel chair ramps on the east side of Denton Tap Road at SE
radius of Braewood and SE radius of Bethel School Road and NE
radius of Bethel Road. 2.) Met with Lacy Co. irrigation
contractor to discuss repairs to existing systems at Medical
Clinic, Steve Parsons' building, First Baptist Church, Ron Van
Ness' building, and Post Office.
10/13/89, Friday (62° - 89°) - olear, sunny
North Projeot
CitY of Dallas Water Utilities - Trench backfill and removal on
concrete thrustblocks on north and south end test plugs. Making
preparations for starting closure sections, scheduled for Monday.
L. H. Lacy Co. - Did not work
South Project
~aale Construction Co. - Doug, 5 men, I bobcat - Forming and
tieing steel for NE wheel chair ramp on Bethel School Road.
Forming sidewalks to Post Office on SE wheel chair ramp on Bethel
School Road. General clean-up on SE wheel chair ramp on
Braewood. Poured concrete for NW wheel chair ramp at Bethel
School Road at 1:15 PM.
Jim Bowman Construction Co. James Long, 7 men - Removing rail
forms from yesterday's concrete pour and re-cycling to south 1/2
of east rail, west bridge. Rubbing, grinding and preparing
imperfections on west rail, east bridge.
~ - Steve, 6 men, 2 grinders, 1 loader - Grinding 2
inside southbound lanes on both north and south crosswalks of
Denton Tap Road at Bethel Road. Switched traffic for southbound
traffic at Denton Tap/Bethel School Road for installation of
brick pavers on the outside 11.5' width lane.
Dave Carlton - 3 men, I backhoe - 3 manhole adjustments
L. H. Lacy Co. - irrigation sub-contractor, Chris, 2 laborers -
Repairs at Steve Parsons' building and at Post Office.
Suma-Stone - 8 men - Did not re-work NW 1/2 brick pavers at
Bethel School Road (see entry on 10/12/89). Working north and
south outside southbound lanes of Denton Tap Road at Bethel
School Road. Outside southbound lane of Denton Tap Road prior to
Bethel School Road closed off. Two inside lanes functioning.
BFooks-Maltbv. Inc. - 3 laborers, I backhoe - Pull box and PVC
sweep installation from Bethel Road to railroad tracks within
median islands. Not installing the required 18" depth of gravel
at pull box locations.
Miscellaneous items - 1.) Met with Tim Brancheau with T.U.
Electric at approx. 10:00 AM regarding power pole and down guy
wire conflicts with wheel chair ramps. 2.) Met Stan Reed, P.E.
and John Karlsruher, P.E. on project at 10:00 AM for coring of
the failed concrete rip-rap slope.