Devonshire 1-CS 921215COPPELL PUBLIC WORKS
DATE:
TO:
FROM:
RE:
December 15, 1992
Steven G. Goram, Director of Public Works
Rey Gonzales, Street Superintendent~
Retaining Wall Along Coppell Road; Concerns Expressed by
Walter Pettijohn
(Tickler 12/15/92)
Staff will need to purchase approximately
terminal end with a terminal post. The
estimate for these items:
-10 Standard Rails (25' sections w/hardware)
-40 Timber Posts
- 1 Terminal End W/Terminal Post
- Delivery Free
250' of rail and one
following is the cost
- $8Z.20 ea. = $ 872.00
$1 .9o ea. = &.oo
- $147.40 = 147.40
TOTAL SA,~
Staff intends to place the order for these materials on the first of
January. Once received, the installation will be done. We anticipate
approximately three working days to complete the project. The first day
will be for setting the timber post and the terminal post. The terminal
post requires time for the concrete to set prior to placing any rail on
it. The second day will be for placing the rail on the timber post and
making sure the alignment is correct. Staff will set the terminal end
on the third day. Next status 1/14/93.
If you have any questions, please let me know.
RG/be
STRETWA.RG