ST8402-CS 891219GINN, INC.
CONSULTING ENGINEERS
December 19, 1989
Mr. Steve Goram, Director of Public Works
City of Coppell
P.O. Box 478
Coppell, Texas 75019
Re: Denton Tap Road Improvements - Executive Summary of Status
Dear Mr. Goram:
As per Mr. Doyle's request we are forwarding an executive summary
which indicates the status of each of the projects through
October 31, 1989. The reason that this report does not cover
progress through November is that the Contractor has not
submitted his application for payment for that period. As
mentioned in last week's city Council meeting, we feel that it is
a bit premature to begin trying to contemplate assessment of
penalties, damages and etc. As you can see there is still a
substantial amount cf work to be completed by the Contractor as
well as requests for additional compensation and contract time
extensions to be evaluated.
In conversations with the project superintendent last week it was
mentioned that L. H. Lacy Co. is anticipating submitting further
claims for additional contract time and compensation which will
have to be evaluated. In cases such as this it has been our
experience that the City of Coppell will be better off to allow
us to receive and evaluate all claims and requests for Change
Orders and negotiate a final contract amount with the Contractor
prior to the City Council considering the assessment of penalties
and damages. The final project report we have mentioned at the
last two city Council meetings will cover all of the issues and
make a recommendation of a final payment amount.
We caution the city only to avoid further complications with the
Contractor. If the Contractor begins to get the idea that the
city intends to rigidly enforce the liquidated damage provisions
of the contract without any other considerations regarding
delays, etc., his efforts may be concentrated on finding ways to
file claims and time extensions to offset liquidated damages
instead of on expeditious completion of the work, which is the
most important and beneficial item for all concerned.
17103 Preston Road · Suite 100 · LB 118 · Dall~
I
r~z~ 7524~: ~ .... 214,'2~'~ :900
Please call us if you have any questions.
Sincerely,
· K~rlsruher,
Project Engineer
enclosures
H. Wayne Ginn, P.E.
Russell Doyle, P.E.
Files J -378 & 379
a:378sgdt
GINN, INC.
Date:
Prepared for:
Prepared by:
Subject:
CONSULTING ENGINEERS
EXECUTIVE SUMMARY
Dece~ber 18, 1989
Honorable Mayor and City Council
Ginn, Inc. Consulting Engineers
Denton Tap Road Improvements from Belt Line Road
to Sandy Lake Road Project Status Through
October 31, 1989.
Paving and Drainage construction is complete with the exception
of small blockouts at the Bethel School Road intersection and
paving markings in some areas.
Bridge construction at Grapevine Creek is complete with the
exception of painting, decorative street light system, and paving
markings.
Seeding for erosion control in progress with rye grass being
planted in the medians, parkways and on slopes. Median grass
will be replaced with bermuda under the Landscape Contract by
others.
We expect final application for payment to be submitted in late
January or early February, 1990.
CONTRACT STATUS:
Original Estimated Contract Amount
Change Orders
Field Changes
Current Estimated Contract Amount
Total work Through October 31, 1989
5% Retainage
Total Amount Remaining (including
retainage)
Original Contract Time (calendar days)
Original Completion Date June 14,
Approved Time Extensions (Change Orders
and Field Changes) (calendar days)
Revised Contract Time (calendar days)
Revised Contract Date (calendar days) July 1,
Actual Time Used through 10-31-89 (calendar days)
Actual Time Used through 12-19-89 (calendar days)
Time Extension Requests Pending (calendar days)
(this would change the contract date to 11-13-89)
$ 3,362,580
(2,415
(13,320
3,346,843
3,059,063
(152,953
440,732
00
60)
84)
56
84
19)
91
365
1989
17
382
1989
504
553
135
There are currently 2 claims for extra compensation due to delays
on file. The time requested for each is reflected above and is
under consideration at this time.
17103 Preston Road · Suite 100 · LB 118 · Dalm% Texas 75248 · Phone 214/2484900
GINN, INC.
CONSULTING ENGINEERS
EXECUTIVE SUMMARY
Date:
December 19, 1989
Prepared for: Honorable Mayor and city Council
Prepared by: Ginn, Inc. Consulting Engineers
Subject:
Denton Tap Road
to Denton Creek
31, 1989.
Improvements from Sandy Lake Road
- Project Status Through October
Paving and Drainage construction is complete with the exception
of paving markings in some areas.
Bridge construction at Cottonwood Branch is complete with the
exception of painting, decorative street light system, and paving
markings.
Seeding
planted
will be
others.
for erosion control is in progress with rye grass being
in the medians, parkways and on slopes. Median grass
replaced with bermuda under the Landscape Contract by
We expect final application for payment to be submitted in late
January or early February, 1990.
CONTRACT STATUS:
Original Estimated Contract Amount
Change Orders
Field Changes
Current Estimated Contract Amount
Total work Through October 31, 1989
5% Retainage
Total Amount Remaining (including
retainage)
Original Contract Time (calendar days) 365
Original Completion Date June 14, 1989
Approved Time Extensions (Change Orders 34
and Field Changes) (calendar days)
Revised Contract Time (calendar days) 399
Revised Contract Date (calendar days) July 11, 1989
Actual Time Used through 10-31-89 (calendar days) 504
Actual Time Used through 12-19-89 (calendar days) 553
Time Extension Requests Pending (calendar days) 135
(this would change contract date to 11-30-89)
$ 1,789,363.03
55,761.27
16,141.80
1,861,266.10
1,718,102.31
85,905.12
229,068.91
There is currently one claim for extra compensation and contract
time extension, and one request for a time extension due to
weather delays on file. The time requested for each is reflected
above and is under consideration at this time.