ST8402-CS 891219GINN, INC. CONSULTING ENGINEERS December 19, 1989 Mr. Steve Goram, Director of Public Works City of Coppell P.O. Box 478 Coppell, Texas 75019 Re: Denton Tap Road Improvements - Executive Summary of Status Dear Mr. Goram: As per Mr. Doyle's request we are forwarding an executive summary which indicates the status of each of the projects through October 31, 1989. The reason that this report does not cover progress through November is that the Contractor has not submitted his application for payment for that period. As mentioned in last week's city Council meeting, we feel that it is a bit premature to begin trying to contemplate assessment of penalties, damages and etc. As you can see there is still a substantial amount cf work to be completed by the Contractor as well as requests for additional compensation and contract time extensions to be evaluated. In conversations with the project superintendent last week it was mentioned that L. H. Lacy Co. is anticipating submitting further claims for additional contract time and compensation which will have to be evaluated. In cases such as this it has been our experience that the City of Coppell will be better off to allow us to receive and evaluate all claims and requests for Change Orders and negotiate a final contract amount with the Contractor prior to the City Council considering the assessment of penalties and damages. The final project report we have mentioned at the last two city Council meetings will cover all of the issues and make a recommendation of a final payment amount. We caution the city only to avoid further complications with the Contractor. If the Contractor begins to get the idea that the city intends to rigidly enforce the liquidated damage provisions of the contract without any other considerations regarding delays, etc., his efforts may be concentrated on finding ways to file claims and time extensions to offset liquidated damages instead of on expeditious completion of the work, which is the most important and beneficial item for all concerned. 17103 Preston Road · Suite 100 · LB 118 · Dall~ I r~z~ 7524~: ~ .... 214,'2~'~ :900 Please call us if you have any questions. Sincerely, · K~rlsruher, Project Engineer enclosures H. Wayne Ginn, P.E. Russell Doyle, P.E. Files J -378 & 379 a:378sgdt GINN, INC. Date: Prepared for: Prepared by: Subject: CONSULTING ENGINEERS EXECUTIVE SUMMARY Dece~ber 18, 1989 Honorable Mayor and City Council Ginn, Inc. Consulting Engineers Denton Tap Road Improvements from Belt Line Road to Sandy Lake Road Project Status Through October 31, 1989. Paving and Drainage construction is complete with the exception of small blockouts at the Bethel School Road intersection and paving markings in some areas. Bridge construction at Grapevine Creek is complete with the exception of painting, decorative street light system, and paving markings. Seeding for erosion control in progress with rye grass being planted in the medians, parkways and on slopes. Median grass will be replaced with bermuda under the Landscape Contract by others. We expect final application for payment to be submitted in late January or early February, 1990. CONTRACT STATUS: Original Estimated Contract Amount Change Orders Field Changes Current Estimated Contract Amount Total work Through October 31, 1989 5% Retainage Total Amount Remaining (including retainage) Original Contract Time (calendar days) Original Completion Date June 14, Approved Time Extensions (Change Orders and Field Changes) (calendar days) Revised Contract Time (calendar days) Revised Contract Date (calendar days) July 1, Actual Time Used through 10-31-89 (calendar days) Actual Time Used through 12-19-89 (calendar days) Time Extension Requests Pending (calendar days) (this would change the contract date to 11-13-89) $ 3,362,580 (2,415 (13,320 3,346,843 3,059,063 (152,953 440,732 00 60) 84) 56 84 19) 91 365 1989 17 382 1989 504 553 135 There are currently 2 claims for extra compensation due to delays on file. The time requested for each is reflected above and is under consideration at this time. 17103 Preston Road · Suite 100 · LB 118 · Dalm% Texas 75248 · Phone 214/2484900 GINN, INC. CONSULTING ENGINEERS EXECUTIVE SUMMARY Date: December 19, 1989 Prepared for: Honorable Mayor and city Council Prepared by: Ginn, Inc. Consulting Engineers Subject: Denton Tap Road to Denton Creek 31, 1989. Improvements from Sandy Lake Road - Project Status Through October Paving and Drainage construction is complete with the exception of paving markings in some areas. Bridge construction at Cottonwood Branch is complete with the exception of painting, decorative street light system, and paving markings. Seeding planted will be others. for erosion control is in progress with rye grass being in the medians, parkways and on slopes. Median grass replaced with bermuda under the Landscape Contract by We expect final application for payment to be submitted in late January or early February, 1990. CONTRACT STATUS: Original Estimated Contract Amount Change Orders Field Changes Current Estimated Contract Amount Total work Through October 31, 1989 5% Retainage Total Amount Remaining (including retainage) Original Contract Time (calendar days) 365 Original Completion Date June 14, 1989 Approved Time Extensions (Change Orders 34 and Field Changes) (calendar days) Revised Contract Time (calendar days) 399 Revised Contract Date (calendar days) July 11, 1989 Actual Time Used through 10-31-89 (calendar days) 504 Actual Time Used through 12-19-89 (calendar days) 553 Time Extension Requests Pending (calendar days) 135 (this would change contract date to 11-30-89) $ 1,789,363.03 55,761.27 16,141.80 1,861,266.10 1,718,102.31 85,905.12 229,068.91 There is currently one claim for extra compensation and contract time extension, and one request for a time extension due to weather delays on file. The time requested for each is reflected above and is under consideration at this time. 17103 Preston Road · Suite 100 · LB 118 · Dallas, Texas 75248 · Phone 214/248-4900