ST8402-CS 891103 COPPBLL PUBLIC WORKS
MBMORANDUM
DATB: November 3, 1989 ~
\\
TO: Steve Goram, Director of Public Works \\k/~
FROM: Howard Pafford, Water Utilities Superintendent .~
RB 16" Waterline Repair at Parkway and Denton Tap/S~
tus Tickler 11/3/89
Completion of the backfill operation was again held up due to the signal contractor needing
to pour the signalpole pier structure.
All that remains is one foot of top soil and fine grading. We will allow the concrete
pier to set-up before charging the water line. Brown Park should have water by Monday
morning.
I will respond with another status report on November 7.
If you have any questions regarding this matter, please advise.
HLP/pd