ST8402-CS 890823GINN, INC.
CONSULTING ENGINEERS
August 23, 1989
Mr. Scot/Balch, P.E.
L.H. L g dy Co.
P.O. ~x 541297
Da~s, TX 75354
R~: Denton Tap Road Improvements from
Sandy Lake Road to Denton Creek
Dear Mr. Balch:
We have been instructed by the City of Coppell to negotiate a
Change Order with L.H. Lacy Co. for the refinishing of the steel
columns beneath the Cottonwood Branch Bridge.
It is our request that you furnish a proposal to perform the work
required under the TSDHPT 1982 Standard Specifications, Item 446,
Protection System 3 - Aluminum. The scope of work shall include
refinishing all col-mns from a point 1 foot below the final grade
of the Cottonwood Branch Channel (see sheet 31 of 56 of the
Contract Drawings) to the top of each column.
Your proposal should include a lump sum price for this work with
a labor and material breakdown and a schedule indicating a
proposed duration for the work referenced herein. We request
that you submit your proposal on or before Friday September 8,
1989.
Please call me if you have any questions.
Sincerely,
John C. Karlsruher, P.E.
Project Engineer
cc: Steve Go~,~
Russel~'DolF/~%' P.E.
Stan ~ed, P.E.
H. Wg~ne G%nn, P.E.
Rand~] Fleming
File 379