RE: Fountain Park Phase II
Final Acceptance
Dear Mr. House:
A final inspection of paving and utilities for the referenced project has been confirmed by
representatives of the City of Coppell.
The two-year maintenance bonds and as-built drawings have been received from the contractor.
Maturity on the bonds will be two years from the date of this letter. Maturity on the Erosion
Control Bond will also be two years from the date of this letter.
Construction Inspector
CCi
Mike Martin, Assistant City Engineer
Doug Stevens, Engineering Technician
Glenn Hollowell, Director of Public Works
Greg Jones, Chief Building Official
Travis Crump, Fire Marshal
Rick Van Guilder, C.W. Young Construction
Lynn Kadleck, Kadleck Associates
Fax (817) 477-1414
Fax (972) 702-0771