March 21, 1990
Mr. Jerry Williams
Landscape Design and Construction,
2559 Southwell Road
Dallas, TX 75229
Inc.
Re: Denton Tap Rsad Landscaping - Coppe11, TX
Dear Mr. Williams:
Enclosed for your files are two (2) sets of executed contract
documents for the above referenced project.
You are hereby notified to commence work on the Denton Tap Road
Landscaping project on or before April 2, 1990, and shall fully
complete all of the work within 120 consecutive calendar days
thereafter. Your completion date is July 31, 1990.
The contract documents provide for an assessment in the sum of
$150.00 per calendar day, as liquidated damages, for each
consecutive calendar day after the above established contract
completion date that the work remains incomplete.
this
By: __
1990.
ACCEPTANCE OF NOTICE TO PROCEED
Receipt of the foregoing
acknowledged by
day of
Notice to Proceed order
1990.
By:
Title:
Landscape Design and Construction, Inc.
is hereby
on this
17103 Preston Road ® Suite 100 · LB 118 · Dallas, Texas 75248 · Phone 214/248-4900
Please sign and return on original for our files.
have any questions, please contact us.
Should you
Sincerely,
Gabe Favre
GF/dsp
cc: Mayor and Council Members
Alan D. Ratliff, City Manager
H. Wayne Ginn, P.E.
John C. Karlsruher, P.E.
J.R. Richardson
File 406