ST8201-CS 900307 (2) GINN, INC.
March 7, 1990
CONSULTING ENGINEERS
Mr. Scott Balch, P.E.
L. H. Lacy Company
P. O. Box 541297
Dallas, Texas 75354-1297
Re: Denton Tap Road Improvements from Sandy Lake Road to Denton
Creek - Final Punch List
Dear Mr. Balch:
We are transmitting herewith the final punch lists developed from
our final inspections of the project over the past couple of
weeks. Included with the punch list items noted by myself in
your presence are the items noted by the City personnel which
have been left in the punch list form in which I received them.
There may be some redundancies in the lists.
Please correct the items indicated on each list. Item No. 21 on
page 4 is to be included as a part of Field Change No. 6, as
noted and its cost must be included in your Final Application for
Payment. All other items will be accomplished at L. H. Lacy
Co.'s expense in accordance with the Contract. Once you have
completed work on these items please call me in order that we may
be able to verify compliance as soon as possible without unduly
delaying final acceptance of the project.
Call me if you have any questions.
Sincerely,
John C. Karlsruher, P.E.
Project Engineer
enclosures
cc:
H. Wayne Ginn, P.E.
Steve Goram - w/enclosure
Howard Pafford - w/enclosur9
Richard Diano - w/enclosure
Dana Kamp - w/enclosure
J. R. Richardson - w/enclosure
)
17103 I rc~ston P, oad · Suite 100 · LB II8 '* Dallas, Texas 75248 · Phm)e 214/248-4900
FINAL INSPECTION PUNCH LIST
PROJECT: Denton Tap Road Improvements from Sandy Lake Road to
Denton Creek, Coppell, Texas
DATE OF FINAL INSPECTION: February 23, 1990
ATTENDEES:
Dana Kamp, City of Coppell Street Dept.
Brent Adams, City of Coppell Street Dept.
J. R. Richardson, Ginn, Inc.
John C. Karlsruher, P.E., Ginn, Inc.
Scott Balch, P.E., L. H. Lacy Company
North bound lanes from Sandy Lake Road to Denton Creek:
5.
6.
7.
8.
Beginning of project, Station 166+58, inside lane curb on
pre-existing section is cracked. Repair crack.
Pull box Sta. 166+60 needs to be reset to grade.
R.O.W. and private property slopes from Sta. 166+58 to
approx. Sta. 178+00 repair erosion damage and provide
permanent erosion control at contractor's expense due to his
use of property for unauthorized borrow source for median
topsoil.
Inlet Sta. 167+27.75 - remove mortar slag from throat.
Patch curb in variable height section of inlet at Sta.
167+27.75.
Inlet in left turn lane Sta. 170+26.32 remove mortar slag
from throat.
North bound left turn lane at Skagg's north driveway -
replace jiggle bar tiles due to soft epoxy.
Clean and seal redwood header at rear of south median nose
at Skagg's north drive median opening (Sta. 170+41.32).
GENERAL NOTE FOR ENTIRE PROJECT:
Clean and seal all paving joints 4ue to sealant too low.
Median nose at Sta. 171+64 clean and seal joints between
the back of curb and median pavement.
~ENER~L NOTE FOR ENTIRE PROJECT:
Clean and seal joints between the back of curb and median
pavement on all median noses.
10. Median nose at Sta. 171+24 - same as item 9. above.
11. Clean and seal redwood header at Sta. 171+53.92.
12. Inlet at Sta. 172+76.50 - remove mortar slag from throat and
clean out interior of inlet.
13. Inlet at Sta. 176+75 - remove saw blade and other
construction debris and clean interior.
14. Clean and seal redwood header at Sta. 177+52.85.
Page 1
North bound lanes (continued):
15. Correct drainage "bird bath" in gutter, outside lanes,
approx. Sta. 177+50.
16. Median nose at Sta. 177+80 - clean and seal joint between
back of curb and median nose pavement.
17. Traffic pull box at Sta. 178+79 - bolt hole damaged - repair
or replace pull box.
18. Inlet at Sta. 179+00 - remove construction debris from the
interior of the inlet and clean interior.
19. Inlet at Sta. 181+00.00 remove mortar slag from throat and
clean out interior of inlet.
20. Traffic pull box at Sta. 181+88 - bolt hole damaged - repair
or replace pull box.
21. Clean and seal redwood headers at Sta. 181+91.32 and Sta.
183+03.92.
22. Median nose at Sta. 182+74 - clean and seal joint between
back of curb and median nose pavement.
23. Inlet at Sta. 183+50 - remove construction debris from the
interior of the inlet and clean interior.
24. Repair landscape berm at the "Parks of Coppell" sign.
25. Inlet at Sta. 185+35.23 - remove mortar slag in throat.
26. Multiple cracks in left turn lane paving from Sta. 184+45.82
to Sta. 186+68.
27. Traffic pull box at Sta. 186+42 - bolt hole damaged - repair
or replace pull box.
28. Median nose at Sta. 187+28 - clean and seal joint between
back of curb and median nose pavement.
29. Clean and seal redwood header at Sta. 187+57.92.
30. North bound left turn lane at Parkway Boulevard - repair
holes in pavement where jiggle bar tiles were removed.
GENERAL NOTE FOR ENTIRE PROJECT:
Remove all construction debris and trash from the medians.
31. Brick paver crosswalk across the north bound lanes on the
south side of the Parkway Blvd./Denton Tap Rd. intersection
replace brick pavers with holes and cracks in them.
32. Brick paver crosswalk across Parkway Blvd. at east side of
the intersection - pavers need more sand and the eastern
concrete edge joint needs repair. Lower the pavers at the
south edge of the crosswalk.
33. Repair the pavers in the Parkway Blvd. median at the east
side of the intersection.
34. Redwood header at east edge of intersection, near the north
curb, needs to be repaired.
35. Correct drainage "bird bath" adjacent to wheelchair ramp
radius at northeast corner of Parkway/Denton Tap.
36. Repair broken traffic buttons in the radius at the northeast
corner of the intersection.
37. Clean and seal redwood header at Sta. 191+75.68.
38. Inlet at Sta. 191+94.64 - Clean out interior and repair face
of inlet.
Page 2
39. Median nose at Sta. 191+53 - repair cracked curb.
40. Replace broken pull box at Sta. 191+79.
41. Patch holes in pavement where traffic buttons were removed.
42. Repair erosion damage to roadway sideslopes and remove
concrete waste and trash from same.
43. Median nose at Sta. 195+58 - Clean and seal joint between
back of curb and median pavement.
44. Traffic pull box at Sta. 200+00 - adjust to conform to
median grade.
45. Remove concrete and stakes from the median.
46. Traffic pull box at Sta. 203+29 - bolt hole damaged - repair
or replace pull box.
47. Remove temporary yellow construction detour centerline
stripes at Denton Creek bridge.
South bound lanes from Denton Creek to Sandy Lake Road:
1. Clean construction trash, debris, and traffic detour barrel
out of the ditch adjacent to the north end of the project.
2. Repair erosion damage on the roadway sideslopes along the
Park. Remove concrete waste and trash from same.
3. Correct drainage "bird bath" in outside lane gutter at south
end of inlet throat blockout Sta. 201+54.5 ±.
4. Inlet/flume at Sta. 201+60 - remove concrete waste.
5. Patch outside curb at bridge approach slab - Sta. 197+99.73.
6. Inlet at Sta. 195+50 - remove mortar slag from throat,
lumber from inside of inlet, clean out interior of inlet.
7. Inlet at Sta. 192+01.96 remove construction debris from
the inside and repair crack in throat.
8. Patch curb in south end of the south variable height curb
for inlet in item 6. above.
9. Correct drainage "bird bath" adjacent to wheelchair ramp at
northwest corner of Parkway/Denton Tap.
10. Brick paver crosswalk across Denton Tap Road south bound
lanes, north side of the Parkway Blvd. intersection -
replace damaged brick pavers.
11. Median nose, Parkway Blvd. west side of the intersection -
repair crack in curb.
12. Brick paver crosswalk across Parkway Blvd., west side of the
intersection - needs more sand in south end of walk and
wheel chair ramp.
13. Correct drainage "bird bath" adjacent to wheelchair ramp in
radius at southwest corner of Parkway/Denton Tap.
14. Correct drainage "bird bath" in outside lane gutter at
approx. Sta. 189+53.
15. Inlet at Sta. 187+50 - remove construction debris from the
interior.
16. Correct drainage "bird bath" in outside lane gutter at north
end of inlet blockout approx. Sta. 187+71 ±.
17. Inlet at Sta. 185+88.94 - remove barricades and construction
debris from the inside of the inlet.
18. Inlet at Sta. 183+50.00 - remove plywood and construction
debris from the inside of the inlet.
19. Redwood header at Sta. 181+91.32 - joint edge in outside
lane is in need of repair.
20. Inlet at Sta. 181+00 remove plywood and construction
debris from the interior and repair crack in the throat.
21. Complete modification of rear opening of inlet at Sta.
176+50 as part of Field Change #6 per Engineer's
instructions.
22. Remove yellow temporary center stripe in south bound lanes
from Sta. 171+00 south to Sandy Lake Road.
23. Repair cracked curb at south header of project (Sta.
166+58).
24. Correct drainage "bird bath" in outside lane gutter at south
side of project header Sta. 166+58.
Also included herein by reference are the punch llsts listed as
follows and attached hereto:
1. Memorandum from Dana Kamp to John Karlsruher dated
2/26/90
2. Memorandum from Richard Diano to John Karlsruher dated
2/22/90
3. Memorandum from Howard Pafford to John Karlsruher dated
2/28/90
FINAL INSPECTION PUNCH LIST FOR COTTONWOOD BRANCH BRIDGE
DATE OF FINAL INSPECTION: February 23, 1990
ATTENDEES: John C. Karlsruher, P.E., Ginn, Inc.
J. R. Richardson, Ginn, Inc.
Stan Reed, P.E., Reedcon, Inc.
1. Rout and seal joints and cracks in approach slabs.
2. Remove construction debris from deck slab sidewalk and
median. Sweep and clean same.
3. Seal all wingwall/riprap joints.
4. Rout and seal all vertical construction joints between new
and old concrete riprap slope protection.
5. Remove loose backfill around guardrail foundations, all
locations, and replace with backfill compacted to 95%
Standard Proctor Density.
6. Repair or replace guardrail attachment at southeast corner
of bridge.
7. Bridge electrical punch list will follow under separate
cover when electrical inspection is completed.
FINAL INSPECTION PUNCH LIST FOR COTTONWOOD BRANCH BRIDGE
LIGHTING SYSTEM
DATE OF FINAL INSPECTION: March 6, 1990
ATTENDEES:
John C. Karlsruher, P.E., Ginn, Inc.
C.R. McCreary, P.E., C.R. McCreary & Assoc.,
Scott Balch, P.E., L.H. Lacy Co.
Bill Brooks (sub-contractor to L.H. Lacy)
Electrical problems prevented operation of light system.
Two breakers tripped, no lights came on. Contractor to work
out problems and re-schedule Final Inspection.