ST8201-CS 900123//Re: Denton Tap Road ImprOvements from Belt Line Road/ Sandy Lake Road ~ Dear Mr. Balch: We have received and reviewed your letter of January 16, 1990 regarding Contract Close-out. We do not agree that the project was substantially complete on September 29, 1989. The improvements were designed as a 6 lane divided thoroughfare and as such were not ready for use as a full six lane divided thoroughfare at that time. We will research our field reports and attempt to determine a date when substantial completion was achieved. As soon as we develop this information we will inform you accordingly. With regard to a final inspection of the project, we feel that it is premature to conduct the inspection prior to your completion of the remaining pay item work on the project. The principal items which need to be addressed prior to the scheduling of a final inspection are: Painting of the Grapevine Creek Bridge Application of all remaining pavement markings traffic buttons and 3. Installation of the bridge lighting system Concreting and installation of brick pavers for the temporary traffic signal pole blockouts at the Bethel School Road intersection In the meantime, we have prepared a partial punch list for the project and transmitted it to you. You have the opportunity, if you choose, to begin work on these items while you complete the unfinished portions of the project. Items which you rectify will be dropped from the list during the final inspection. We caution you that these punch lists are by no means final or complete, but are furnished to you as a courtesy in hopes that they will help you finalize the project as soon as possible. 17103 Preslo. Road · Suite 100 · LB II8 · Dallas, Texas 75248 · l'hoae 214/248-4900 The City of Coppell has requested that you submit, through our office, your anticipated schedule for the final completion of the project. Please call if you have any questions. Sincere ly, John C. Karlsruher, P.E. Project Engineer co: Steve Goram, Director of Public Works File 378 January 16, 1998 Mr. John C. Karlsruher, P.E. Ginn, Inc. 17103 Preston Road, Suite 100, Dallas, TX '752q8 RE: Denton Tap Road Improvements Beltline Road to Sandy Lake Road Contract Closeout Dear' Mr. Karlshurer: In accordance with Section Ol?00-CONTRACT CLOSEOUT, this letter shall serve as written notice that the project is substantially complete. On September 29, 1989~ the northbound traffic was switched to the east side of the median from Beltline Road to Braewood Street. At that time we considered the project substantially complete, i.e. the facility was serving its intended purpose. Some of tire A. B. C. D. E. F. G. H. I. items of work remaining at that Complete bridge railing. Set remaining pull boxes. Pavers for southbound lanes. Complete ~heelchair ramps. Complete pavement markers for Construct guardrail. Complete channel grading. Complete bridge lighting. southbound lanes. Construction of left turn lanes for Meadow and Baptist Foundation, including related items. Creek Since September 29, 1989, we have pursued the expedient completion of the items mentioned above as well as various cleanup items. At this time we would like to request an inspection of the project be made to determine the status of completion and subsequently provide us with a list of items of work to be completed or corrected. We are aware that there is still some work to be done on a few of the items listed above. However~ we 'feel those can be added to your final list. We look forward to receipt of a Certificate of Substantial Completion and appreciate YOur consideration. Respectfully, Scott J. Balch, P.E. Senior Project Manager L. H. Lacy Company General Contractors 214/357-0146 "Oualily Construction lot over 65 Years" 10888 Shady Trail P.O. Box 541297 Dallas. Texas 75354-1297