Fairways-CS 921106The City With A Beautiful Future NOV i CJ pell, Texas 75010 1 0 1992 / i214~462-0022 PUBLIC WORKS November 6, 1992 ~ A '~/~'~~ Mr. Mike Daniel, P.E. Nathan D. Maier Consulting Engineers Three Northpark/8800 N. Central Expressway, Ste. Dear Mr. Daniel: Enclosed is a copy of the City of Coppell Development Fee Assessment list, along with a copy of the development fee calculations for the Fairways at Riverchase. Please provide a check made payable to the City of Coppell in the amount of $116,557.12 plus 2% of the construction cost and forward it to Mr. Alan Johnson, Assistant Finance Director, Finance Department, along with a copy of the fee assessment list. This should be provided prior to City Council approval of the final plat. Also, please provide our office a copy of the Engineer's Estimate or contract for this project so the construction inspection fee can be verified. Please provide a copy of your paid receipt to our offices. Copies of your receipts will help us verify payment of the required fees and assure a successful beginning of this project. We look forward to working with you on this project. If you have any questions, please do not hesitate to contact me. Sincerely, Kenneth M. Griffin, P.E. City Engineer CCl Steve Goram, Director of Public Works Alan Johnson, Assistant Finance Director Greg Jones, Acting Building Official fairways Date: Project: C1TYOF COPPELL DEVELOPMENT FEES November 6, 1992 Fairways at Riverchase Park Fee (50% due prior to Council Approval) (50% due at Issurance of Building Permit) TOTAL ASSESSMENT $ 14,700.00 Water Impact Fee (100% due prior to Council Approval) $ 63,700.00' Water Tap Inspection Fee (100% due at Issuance of Building Permit) $ 9,800.00 Wastewater Impact Fee (100% due prior to Council Approval) $ 44,100.00 Sewer Tap Inspection Fee (100% due at Issuance of Building Permit) $ 9,800.00 Utility Final Inspection Fee (100% due at Issuance of Building Permit) $ 4,900.00 Street Sign Fee (100% due prior to Council Approval) $ 1,407.12 Street Light Fee (100 % due prior to Council Approval) Construction Inspection Fee (2% of Project Cost: 100% due prior to Council approval) Total $148,407.12 TOTAL AMOUNT DUE PRIOR TO COUNCIL APPROVAL AMOUNT DUE PRIOR TO COUNCIL APPROVAL $ 7,350.00 $ 63,700.00* $ 44,100.00 $ 1,407.12 $116,557.12 $116,557.1234 +2%inspectionfee * The water impact fees do not include the fees for the irrigation meters. ** This fee cannot be assesed until after TU Electric submits the lighting plan for the proposed project. Once the plan is submitted, $292.60 per light will be assessed. COPPELL PUBLIC WORKS The following fees project. November 2, 1992 Ken Griffin, City Engineer Public Works Staff Development Fees for The Fairways at Riverch&se should be assessed on the above referenced Water Impact Fee: 98 - Domestic Meter/s = 98 ESU's Irrigation Meter/s = ESU's Fireline Meter/s = ESU's Total 98 ESU's ~ $650.00 ea = $63,700.00 100% due prior to Council approval of final plat. * This assessment does not include irrigation meter impact due to that information not being available at this time. Wastewater Impact Fee: 98 - 5/8"x$/4" Domestic Meter/s = 98 ESU's ~ 450.00 = $44,100.00 100% due prior to Council approval of final plat. Water Tap Inspection Fee 98 Connections @ $100.00 each = ~9,800.00 100% due prior to issuance of building permit. Sewer Tap Inspection Fee 98 Connections ~ $100.00 each = $9,800.00 100% due prior to issuance of building permit. Utility Final Inspection Fee 98 Residential Homes @ $50.00 each = $4,900.00 100% due prior to issuance of building permit. Street Lighting Fee Shall be assessed and paid prior to final acceptance of project. Note: This fee cannot be assessed until after TU Electric submits the lighting plan for the proposed project. Once plan is submitted $292.60 per light will be assessed. Street Sig~s Fee See attached Street sign assessment sheet. 100% due prior to final acceptance of project. Park Fee 98 Residential Lots at $150.00 each = $14,700 Units (Multi family) at $75.00 each = 50% of the amount specified above shall be paid by the Developer; prior to Council approval of final plat. 50% remaining shall be paid by the Builder at such time as a building permit is issued. Please advise the Developer of these fees and due dates. If you have any questions regarding these assessments please advise. HLP/dm CC: Steven G. Goram, Director of Public Works STREET SIGN ASSESSMENT for The Fairways ~ Riverchase The following assessment is being made in accordance with the City of Coppell Subdivision Ordinance Appendix A chapter VIII A. The following cost of those sign materials required are based on current pricing which is reviewed on a regular basis. SIGN UNIT PRICE QUANTITY EXTENDED PRICE No Parking $ 53.10 Speed Limit $ 63.54 13 $ 826.02 Yield $ 58.56 Stop $ 65.12 Street Name $ 11.60 Stop & Street Combo $ 96.85 6 S 581.10 OTHER TOTAL Sl.407.12 * Cost breakdowns may be obtained from Public Works by written request. fairwy.