ST9301A-CS 951113 i: rvsuc
November 13, 1995
Mr. Lloyd James, P.E., Project Manager
Charles Gojer and Associates, Inc.
Consulting Engineers
11615 Forest Central Dr. #204
Dallas, Texas 75243
Re: Sandy Lake Project 91-838
(Coppell E. City Limits to Carrollton City Limit)
Your letter dated October 25, 1995
Dear Mr. James:
This letter is in response to your letter dated October 26, 1995
concerning the typical section on the bridge and the proposed storm
sewer route for the 66" line. For ease of reference I will follow the
format of your letter.
Regarding topic A; we have studied a recommendation indicated on your
enclosed sketch. In addition, we have discussed your recommendation
with various City officials. Attached you will find a copy of your
submittal which has been marked-up to reflect the desires of the
various public officials. As a further aid to you comments to your
sketch follow:
1. Remove the raised median section. Use the median barrier
wall (with no raised median) previously shown on your
plans.
2. Remove barrier walls that separate the interim travelled
way (inside lanes) and the space available for future
lanes. Delineation is to be handled by two rows of white
buttons (minimum size of buttons is 8"). Use of buttons
will enable easy adaptation in the future for widening or
adding lanes by the City.
3. Reposition the 501 Rail to the both outside edges using the
same out to out dimension.
4. No raised sidewalk is to be provided on the bridge but it
is to be provided at both ends of the bridge. GTE will be
asked to propose another method for supporting their
conduit.
411 Elm 'Street Dallas, Texas 75202 653-7151
Mr. Lloyd James, P.E., Project Manager
November 13, 1995
Page Two
Regarding topic B; as previously indicated to you verbally, we have
studied your comments concerning the proposed route and concur with
your recommendations relative to the minor alignment changes. Please
complete design of this line as soon as possible.
As always, you may call me at 653-6423 if you have questions
concerning the above.
Sincerely,
Irvin S. Griffin, P. E.
Project Engineer
ISG/isg "' ~ ~
~. Ken Griffin, P.E., City of Coppell
Tim Tumulty, P.E., City of Carrollton