April 16, 1999
Mr. Kenneth M. Griffin, P.E.
Director of Engineering and Public Works
City of Coppell
255 Parkway Blvd.
Coppell, Texas 75019-4409
Re~
Sandy Lake Road Reconstruction
Coppell Project #: ST 93-02
Kimley-Hom Project #: 06940600
DWU Project #: 98-31IF
Dear Mr. Griffin:
Enclosed for your review and incorporation into the contract are three executed copies of change
order #1.
If you have any questions regarding this change order, don't hesitate to contact our office.
Sincerely, __
~ ~~ction Company
Robert D. Weber
Project Engineer