June 8, 2000
Gregory Weisbmch
1613 Live Oak Dr.
Irving, TX 75061
Heartz Road Addition:
Fee Assessment Letter
Park Development Zone: Zone 2
Dear Mr. Weisbmch:
Enclosed is a copy of the City of Coppell Development Fee Assessment table, along with
a copy of the Development Fee calculations for the referenced development.
Please make payment to the City of Coppell in thc amount of $3.040.00 and forward to
the Finance Department along with a copy of the Fee Assessment table. This amount is a
portion of the assessed fees that need to be paid prior to Council approval. Also provide a
copy of the Engineer's estimate or contract to our office so the construction inspection
fee can be verified.
Providing a copy of your paid receipt to the Engineering Depathnent will help us to
verify the payment of required fees and insure a successful beginning of this project. We
look forward to working with you on this project. If you have any questions, please
contact me.
Sincerely,
Kent M. Collins, P.E.
Civil Engineer
CC:
Jennifer Armstrong, Finance Director
Debbie Ingram, Secretary
Gl~m Hollowdl, Assistant Director of public Worlm
Greg Jones, Chief Building Official
Gary Sims, Director of Leisure Services
DEVELOPMENT FEE TABLE
Project: Heartz Road Addifi. on
Date: 06/08/2000
TOTAL AMOUNT DUE
FEES DUE PRIOR TO
COUNCIL
APPROVAL
Water Impact Fee $450.00 $450.00
(100% due prior to Council Approval)
Water Tap Inspection Fee $50.00
(100% due at Issuance of Water Meter)
Water Meter Fee (Domestic) $25.67
(100% due at Innllance of Water Meter)
Water Meter Fee (In-igation~ireline) $0.00
(100% due at lanuance of Water Meter)
Water Meter Deposit (Domestic) $35.00
(100% due at Issuance of Water Meter)
Irrigation/Fireline Meter Deposit $0.00
(100% due at Issuance of Water Meter)
Wastewater Impact Fee $450.00 $450.00
(100% due prior to Council Approval)
: Wastewater Tap Inspection Fee $50.00
(100% due at Issuance of Building Permit)
Utility Final Inspection Fee $50.00
(100% due at Iss-ance of Building Permit)
Park Fee $1,285.00 $1,285.00
(100% due prior to Council Approval)
Roadway Impact Fee $855.00 $855.00
(100% due prior to Council Approval)
Street Light Fee ~nformation not Available
(100% due prior to Acceptance of Project
Street Sign Fee Information not Available
(100% due prior to Acceptance of Project
Construction Inspection Fee Information not Available
I'OTAL $3,250.67
TOTAL AMOUNT DUE PR/OR TO COUNCIL APPROVAL $3,040.00
DEVELOPMENT FEE WORKSHEET
PROJECT: lteartz Road Addition
DATE: 06/08/2000
Water Impact Fee:
Domestic Meter(s):
Irrigation Metar(s):
I - 5/8 inch X3/4 inch = I
0 = 0
0 = 0
Fireline Meter(s): 0 = 0
Total #: 1 ESU's @ $450.00 ea,
(100% due prior to Council approval of the final plat)
Water Tap Inspection Fee:
Total #: I Connections @ $50.00 ea.
(Single family due prior to issuance of building permit)
(All other developments due prior to issuance of meter)
Domestic Water Meter Fee:
Total #: 1 Domestic Meter(s) @ $25.67
(Single family due prior to issuance of building permit)
(All other developments due prior to issuance of meter)
IrHgatio~fFireli~e Water Meter Fee:
Total #: 0 Irrigation Meter(s) @ $0.00
Total #: 0 Additional Irrigation Meter(s) @ $0.00
Total #: 0 Fireline Meter(s) @ $0.00
(100% due prior to issuance of water meters)
Domestic Water Meter Deposit Fee:
Total #: I Meter(s) @ $35.00 ea.
(100% due prior to issuance of water meters)
Irrigation/Fire Meter Deposit Fee:
Total #: 0 Meter(s) @ $30.00 ea.
(100% due prior to issuance of water meters)
Wastewater Impact Fee:
Total Domestic Meters ESU's:
@ $450.00 ea.
Wastewater Tap Inspection Fee:
Total #: 1 Connections @ $50.00 ea.
(100% due prior to issuance of building permit)
Utility Final Inspection Fee (All developments):
Total #: 1 Lots @ $50.00 ea.
(100% due prior to issuance of building permit)
ESU's
ESU's
ESU's
ESU's
$450.00
$50.00
$25,67
$0.00
$0.50
$0.00
$35.00
$0.00
$450.00
$50.00
$50.00
Page I
DEVELOPMENT FEE WORKSHEET
Park Fee (For Residential Developments Only):
* Preliminary plat approved: After October 26, 1993
Park Development Zone:
1 Single-family ~ $1,285.00 per lot
0 Multi-family @ $1,285.00 per unit
(50% paid prior to Council approval of final plat)
(50% paid at issuance of building permit)
Roadway Impact Fee:
(See attached fee calculations)
Street Lighting Fees:
Assessed for lighting in the City's right-of-way.
This fee cannot be assessed until after T.U. Electric submits
the lighting plan for the proposed development.
Once the plans are submitted, $292.60 per light will be assessed.
(100% due pdor to final acceptance of development)
Zone 2
$1,285.OO
$o.oo
$855.00
Information' not Available
Street Sign Fees:
Assessed for signage in the City's right-of-way.
(See attached fee calculations if applicable)
Information not Available
Construction
Inspection Fees:
A copy of the development contract must be submitted for assessment.
The contracts should indicate the cost to construct the improvements
that are inspected by the Engineering Department.
(2% of development cost required for private improvements)
(4% of development cost required for public improvements)
Information not Available
P~e2
ROADWAY IMPACT FEE CALCULATIONS
PROJECT: Hem'tz Road Adition
DATE: 06/08/2000
ROADWAY IMPACT FEE:
5~tviee Area * 6
Category ** Residential
Land Use ** Sin$1~Family Detached
No. Lots/Units 1
Development Units ** 1.00
Vehicle Mil~ per Development Unit ** 2.85
Fee per Velfigle Mile *** $300
Roadway Impa~ Fee du~ = (Developazat Units) x
Yehiele Miles ~r Development Unit) x (Fee per Vehicle Mile) = $855.00
* (Figure 2 - Roadway Impact Fee Study)
** (Table 3 - Roadway Impact Fee Study)
*** (Schedule 2, Page 3 - Roadway Impact Fee Study)