Gateway BP (1.1)-CS 950222The City With A Beautiful Future
February 22, 1995
P. O. Box 478
CoppelI, Texas 75019
214- 462-0022
FAX 214- 393-0948
Mr. Pat Acker
Halff and Associates
8616 North Plaza Drive
Dallas, ~Texas 75225
RE: Freeport Parkway Sanitary Sewer Line Repairs
Dear Mr. Acker:
As per our discussion regarding the repairs that need to be
performed on the Freeport Parkway Sanitary Sewer Line, you had
asked me to prepare a quote for city staff to make these repairs.
Attached you will find a quote for two point repairs and clean-up
of the entire system.
If the owner of the development wants the work performed by city
staff, please have a check cut for the amount listed and the work
will be completed within 60 days.
If you have any questions regarding this matter, please contact
me at 304-354
~~~rSi erely,
Utilities Su ~tendent
HLP/dg
City of Coppell
Water Utilities
REPAIR QUOTE
Point Repair # 1 Sta. 0+00.00 Line "B"
1 - Crewleader 12 hrs.
2 - Maintenance Workers 12 hrs.
Repair Materials all
Backhoe time 6 hrs.
Shoring Box
@ 13.00 hr.
@ 9.00 hr.
@ 50.00 hr.
@ 35.00 hr.
@ 100.00 all
Total Cost Repair #1
Point Repair # 2 Sra. 4+00 Line "A"
1 - Crewleader 8 hrs.
1 - Maintenance Worker 8 hrs.
Repair Materials (Grout)
Grouting Unit 2 hrs.
Entry Equipment 3 hrs.
@ 13.00 hr.
@ 9.00 hr.
@ 150.00 all
@ 100.00 hr.
@ 50.00 hr.
Total Cost Repair ~2
Cleaning of System
i - Crewleader
1 - Maintenance Worker
Vactor Unit
8 hrs. @ 13.00 hr.
8 hrs. @ 9.00 hr.
6 hr.s @ 45.00 hr.
Total Cost for Cleaning
$ 156.00
216.00
50.00
210.00
100.00
$ 732.00
$ 104.00
72.00
150.00
100.00
150.00
$ 576. O0
$ 104.00
72.00
270.00
$ 446.00
Total Repair and Cleaning Cost $1,754.00