Loading...
ST9302-UP 990501SANDY LAKE ROAD CONSTRUCTION Progress Meeting Held The 6th and 7th progress meetings were held on April 20th and May 18th. The main topic of discussion in both progress meetings was the lowering of the 16" water line at various locations along Sandy Lake Road. Utility Relocations TU Electric has nearly completed their relocations along Sandy Lake Road. Paragon Cable still has fiber optic cable to relocate from Moore Road to MacArthur Blvd. which may impact the operation of the traffic light at the Moore/Sandy Lake intersection. Lone Star Gas continues their relocations. There have been several issues raised about the work area after Lone Star Gas has performed their relocations. Please keep us informed of any issues as we also can contact Lone Star Gas on your behalf for. necessary repairs. Our latest estimate is that utility relocations will be complete by the end of June. Since Last Update Since the last update, approximately 1574 linear feet of 30" water line has been installed from Denton Tap to east of Trailwood. Also, approximately 300 linear feet of 16" water line has been lowered. About 180 feet of the 16" water line lowering took place near the Minyard Shopping Center. Prior to that lowering, a temporary water service was installed to ensure that the new shopping center on the north side of Sandy Lake had fire protection during the lowering of the 16" water line. About 120 feet of the 16" water line lowering was at Moore Road. Prior to that lowering, a permanent May 1999 Ken Griffin, Director of Engineering water line was installed on the south side of Sandy Lake to provide water service to the shopping center at the southeast corner of the Moore /Sandy Lake intersection. Also, the coacrete channd on the east end of the project has been completed. However, there is still minor work to be completed such as grading around the channel and hydromulching. Current Issues As previously mentioned, approximately 120 feet of water line has been lowered in the Moore Road intersection. The overall lowering at Moore is approximately 200 linear feet. However, the last 80 feet is at best a challenge. Since the beginning of the project there has been apprehension about working in the Moore/Sandy Lake intersection due to the number of existing utilities. Even after uncovering several of the utilities to verify locations, reviewing as-built plans, etc., utilities underground are stiN. not as we expected. The majority of the May 18'~ progress meeting was spent discussing how to accomplish lowering the last 80 feet of the 16" water line, without totally shutting down the Moore/Sandy Lake intersection to traffic. Current conflicts include an existing 5' x 2' box culvert, existing sanitary sewer manhole, existing 16" gas line and potentially other utilities that may or may not be in conflict as we proceed eastward. Several designs have been provided to Lone Star Gas Company to cross over the existing gas line. Our last design has been approved; ff there is no variation in the actual installation of the gas line from what the plans show. To accomplish the crossing of the existing 5' x 2' box culvert several sections of the existing box culvert Project ST 93-02 Denton Tap to MacArthur have to be removed and replaced with the permanent 66" reinforced concrete pipe. The pipe is approximately 7' feet lower than the existing box. However, to ensure proper drainage there still has to be a transition from the box to the pipe. This will require work in the Moore /Sandy Lake intersection. The sanitary sewer manhole will be removed and the sewer line repaired. There are manholes both north and south of this manhole to ensure proper cleaning and access to the sewer line. If the solutions to the problems work in the field, it is anticipated that the 16" water line lowering through the Moore/Sandy Lake intersection will be completed by May 26~. Testing of the 16" water line will then take place and if all items pass it could be put back into service as early as May 28~. Complaints / Concerns Any complaints or concerns should be addressed first to Start Phillips, the City's project inspector. Once Start has received notice of an issue normally it can be resolved. If not, he then forwards the issue to my office for my involvement. Some issues such as damage by the franchise utility companies are not as rapidly resolved, as those companies work under a franchise agreement and have the right to install their facilities within the City's right- of-way. They do not work under the direct supervision of the City of Coppell nor do they supply plans or schedules to the City on their anticipated work. If you are unsuccessful in resolving an issue with the franchise utility companies please feel free to contact either Stan Phillips or my office and we will contact the utility companies on your behalf. Please understand that we are not always entirely successful in getting the utility companies to rapidly respond to your request. Damage, which no one takes responsibility for, takes longer to address. Your patience in allowing the City to resolve these issues is appreciated. In the Future Contractor will continue to work on the 16" water line lowering. Once they complete the Moore Road section, the Samuel portion still May 1999 Ken Griffin, Director of Engineering has to be lowered. Concurrent with lowering the 16" line, the contractor wm continue to work on the 30" water line. We have tried to minimize any side street closures from 9:00 a.m. to 4:00 p.m. only. A copy of the updated project schedule is being provided with this newsletter. Use the schedule as a general guideline, as the schedule has already been delayed approximately 3 weeks because of utility conflicts in the Moore/Sandy Lake intersection. The schedule shows the contractor will begin setting up for the north side paving sometime in July, but according to the contractor it will be closer to the ~rst part of August. Our June 15"' progress meeting will be focused on the north side paving and traffic control. The traveling public will be inconvenienced during the paving of Sandy Lake Road by virtue of the equipment working along the shoulder of the road, any transition from the old paving to temporary paving and potentially any detours necessitated by the paving itself. As always we will strive to work with the contractor to ensure that any inconveniences are kept to an absolute minimum. Contact Numbers ·Stan Phillips, City's Project Inspector 972/745-6592 pager 214/877-3483 · Gary Pryor, Contractor's Superintendent 214/358-6581 · Ken Griff'm 972/304-3686 · Mike Martin 972/304-3679 · After hours emergency Police Department 972/304-3610 E-mail addresses (Non-emergency) · Ken Griff'm - k.m-iff'mt~ci.coooell.tx.us · Mike Martin - mmartin~d.co0oell.tx.us · Lee Alli.~on - lalison~kimle¥-horn.com City's consultant w/Kimley-Horn Engineers · Robert Weber - robertw8~airmail.net Project Manager w/Ed Bell Construction Web site · www.ci.coppell.tx.us/en~ineer/en~neer.htm Projec~ ST 93-02 Denton Tap to MacArthur 1999 '2000 ~ 1~., I~y I.M.., ].[w I~.~., I~"'''d'~ I°''d'~ I~ I~