The contractor has completed approximately 80% of this project. He
is currently installing the last of the culvert pipes under the
drives on Bullock and will be installing an additional 260 L.F. of
ADS pipe in the cul-de-sac on Bullock. If the weather permits, he
should have the driveways poured back, asphalted or based up bythe
end of next week. Next status 6/9/92.