January2,1999
Mr. Kenneth M. Griffin, P.E.
Director of Engineering and Public Works
City of Coppell
255 Parkway Blvd.
Coppell, Texas 75019-4409
Re~
Sandy Lake Road Reconstruction
Coppell Project #: ST 93-02
Kimley-Hom Project #: 06940600
DWU Project #: 98-311F
Dear Mr. Griffin:
As you are aware the existing storm sewer junction structure shown at STA 55+39.37 Lt. is
actually closer to the proposed roadway centerline than is shown on the plans. As a result, the
proposed 21" storm sewer lines to the east and west of Moore Road will need to be connected
into the existing 66" storm sewer. As requested, our utility subcontractor, M-Co Construction,
has submitted pricing for those field connections. Our price for each of the two pipe to pipe
connections is $825.00. Please add an additional two calendar days to the project's duration for
this work.
If you have any questions regarding this issue, don't hesitate to contact our office.
Sincer,e, ly,
~-Bm~ C~onst~'i~ction Company
Robert D. Weber
Project Engineer