ST9301-CS 990430 '~
ANDY LAKE ROAD PROJECT 91-630
(MacArthur Boulevard to Coppell City Limits)
Project Status Report
30, ]999
PROJECT ENGINEER:
PROJECT LOCATION:
PROJECT DOLLARS:'
John L. Mears
District 1; City of COppel!
Authorization =
$ 7,600,000
*Belt Line Rd. (91-829) and Sandy Lake Rd. (91-830) in 1991 Bond Fund at $7.6 million.
TOTAL PROJECT COST
County Construction = $ 4,400,000
Contingencies (5%) = $ 220,000
'ROW Acquisition = $ by City
Administrative Costs = $ 352,000
Design = $ 129,87.2
Materials Testing (1.5 %) = $ 44,000
Railroad Crossing/Signal = $
Total Project Cost = $ 5,145,872
Additional City of Coppell (Utilities) = $ (est.) 350,000
Elelt Line Rd. ¢91-829) and Sandy Lake Rd. (91-830) in 1991 Bond Funding at 7.6 million. Belt Line Rd. proj
~ct
to be completed.
Consultant/Award/Work Order/Contract Total
Sverdmp Corp. Consulting Engineers/9-1-92/10-9-92/$129,872
Status = revising preliminary plans (80%)
Issues/Conflicts = proposed contract amendment for design/easements
Woodridge box culvert
Completion -- JUL 99 without contract amendment work;
OCT 99 w/contract amendment
ROW:
Number of Parcels = 28 (est)
Status -- 75 %
Status of Acquisition = By City
Eminent Domain
Agreements
Issues/Conflicts
Completion =
Utility Release = NOV 96
Utilities to be Cleared
Status of Work
Agreements
ISSH. es/Con flictS.
Completion =
CONSTRUCTION:
Advertisement =
Contractor/Award/Work
Order/Total Contract
Working Days
Status
Issues/Conflicts
Completion =
830.PSR