Gibbs Station 2-CS 930723 (2)Suly 23, 1993
P,O. Box 478
Coppell, Texas 75019
214-462-0022
Mr. Bill Anderson
Dowdey Anderson & Associates, Inc.
16250 Dallas Parkway
Suite 100
Dallas, TX 75248
RE: Gibbs Station Phase H
Development Fee Assessment
Dear Mr. Anderson:
Enclosed is a copy of the City of Coppell Development Fee Assessment list, along with a copy
of the development fee calculations for Gibbs Station Phase II.
Please provide a check made payable to the City of Coppell in the amount of $144,512.59 and
forward it to Mr. Alan Johnson, Acting Finance Director, along with a copy of the fee
assessment list. Please provide our office a copy of the Engineer's Estimate or contract for this
project so the construction inspection fee can be verified.
Please provide a copy of your paid receipt to our offices. Copies of your receipts will help us
verify payment of the required fees and assure a successful beginning of this project.
We look forward to working with you on this project. If you have any questions, please do not
hesitate to contact me.
Sincerely,
KennethM.~fi'ffin,
City Engineer
Steve Goram, Director of Public Works
Alan Johnson, Acting Finance Director
Greg Jones, Building Official
Doug Stevens, Engineering Technician
CITY OF COPPELL
DEVELOPMENT FEES
Date:
Project:
July 23, 1993
Gibbs Station Phase H
TOTAL
AMOUNT DUE
PRIOR TO COUNCIL
Water Impact Fee $ 83,200.00 $ 83,200.00
(100% due prior to Council Approval)
Water Tap Inspection Fee $ 12,400.00 $ -0-
(100% due at Issuance of Building Permit)
Wastewater Impact Fee $ 27,675.00 $ 27,675.00
(100% due prior to Council Approval)
Sewer Tap Inspection Fee $ 12,300.00 $ -0-
(100% due at Issuance of Building Permit)
Utility Final Inspection Fee $ 6,150.00 $ -0-
(100% due at Issuance of Building Permit)
Water Meter Fee (Lots) $ 2,736.75 $ -0-
(100% due at Issuance of Building Permit)
Water Meter Fee (Irrigation) $ 157.00 $ -0-
(100% due at Issuance of Building Permit
Irrigation Meter Deposit $ 35.00 $ 35.00
(100% due prior to issuance of Water Meters)
Water Meter Deposit $ 3,690.00 $ -0-
(100% due at Issuance of Building Permit)
Street Sign Fee $ 1,034.40 $ 1,034.40
(100% due prior to Acceptance of Project)
Street Light Fee $ * $
(100 % due prior to Acceptance of Project)
Park Fee $ 43,050.00 $ 21,525.00
(50% due prior to Council Approval)
(50% due prior to Issuance of Building Permit)
Construction Inspection Fee
(2% of Project Cost due prior to
Preconstruction Meeting)
Total
$12,077.59
$204,505.74
TOTAL AMOUNT DUE PRIOR TO COUNCIL APPROVAL
$12,07759
$144,512.59
$144,512.59
+2% inspection fee
* See attached memo
COPPELL PUBLIC WORKS
MEMORANDUM
DATE:
TO:
FROM:
RE:
The following
proj e ct:
July 22, 1993
Doug Stevens, Engineering Technician
Public Works Department
Development Fees for Gibbs Station Phase II
fees should be assessed on the above
referenced
Water Impact Fee:
123 - %" x ~"
1 - 1~"
Domestic Meter/s = 123 ESU's
Irrigation Meter/s = 5 ESU's
Total 128 ESU's ~ $650.00 ea = $83,200.00
100% due prior to Council approval of final plat.
Wastewater Impact
123 - %" x %"
Total 123
100% due prior to Council approval
Residential meters = 123 ESU's
ESU's ~ $225.00 ea = $ 27,675.00
of the final plat.
Water Tap Inspection Fee
124 Connections ~ $100.00 each = $ 12.400.00
100% due prior to issuance of building permit. (Or in the case of
the irrigation meter-prior to issuance of meter).
Sewer Tap Inspection Fee
123 Connections ~ $100.00 each = S12.300.00
100% due prior to issuance of building permit.
DEVELOPMENT FEES
Page 2
UtilityFinal Inspection Fee
123 lots ~ S50.O0/lot = S6.150.00
100% due prior issuance of building permit.
Water Meter Fee (Lots)
123 - ~" x ~" Residential Meters @ $22.25 ea
100% due prior to issuance of building permit.
= $2,736.75
Water Meter Fee (Irrigation)
1 - 1%" Irrigation Meter @ $157.00 ea
Total
100% due prior to issuance of water meters.
= $157.00
= $157.00
Water Meter Deposit
Residential - 123 meters @ $30.00 ea = $3,690.00
lO0% due prior to issuance of building permit.
Irrigation Meter Deposit
1 1%" meters @ $35.00 ea = $35.00
Total = $35.00
100% due prior to issuance of water meters.
Street Lighting Fee
Shall be assessed and paid prior to final acceptance of project.
Note: This fee cannot be assessed until after TU Electric
submits the lighting plan for the proposed project. Once
plan is submitted, $292.60 per light will be assessed.
Development Fees
Page $
Street Signs Fee
See attached Street Sign Assessment sheet.
100% due prior to final acceptance of project.
Park Fee
Residential Lots ~ $150.00 ea = $
Units (Multi-family) ~ $75.00 ea = $
For those developments having preliminary plat approval prior to
June 23, 1992 the following assessment is determined:
50% of the amount specified above shall be paid by the Developer;
prior to Council approval of final plat.
50% remaining shall be paid by the Builder at such time as a
building permit is issued.
For those developments having preliminary plat approval after June
23, 1992 the following assessment is determined;
123 Residential Lots @ $350.00 ea = $43,050.00
Units (Multi-family) at $350.00 ea = $
50% of the amount specified above shall be paid by the Developer
prior to Council approval of final plat.
50% remaining shall be paid by the Builder at such time as a
building permit is issued.
Please advise the Developer of these fees and due dates.
If you have any questions regarding these assessments please
advise.
Development Fees
Page 4
STREET SIGN ASSESSMENT
for
Gibbs Station Phase II
The following assessment is being made in accordance with the city
of Coppell Subdivision Ordinance Appendix A Chapter VIII A. The
following cost of those sign materials required are based on
current pricing which is reviewed on a regular basis.
SIGN
UNIT PRICE QUANTITY
EXTENDED PRICE
No Parking
$53.10
speed Limit 63.54 10
Yield 58.56
Stop 65.12
Street Name 11.60 ~
Stop & Street Combo 96.85 4
OTHER
No Outlet 11.60 1
$635.40
387.40
11.60
TOTAL $1,034.40
Cost breakdowns may be obtained from Public Works by written
request.
HLP/dm
cc: Steven G. Goram