ST8601-CS 910220COPPELL PUBLIC WORKS
MEMORANDUM
DATE:
TO:
VIA:
FROM:
HE:
February 20, 1991
Steven G. Goram, Director of Public Works
Daneshmand, Acting City Eagiaeer~i~
Shohre
Larry Da~Construction Inspector
MacArthur North Extension
Tickler 1-10-91
The inspection cost for the above referenced project is
$14,300.00, based on inspection time, vehicle expenses, benefits,
and plan review.
The Engineering firm of Carter and Burgess has been requested to
proceed with forwarding payment of the estimated inspection cost.
The projected completion time for this project is June 1991. Ail
fees related to the project will be collected before a final
acceptance of the project.
We will keep you informed of the progress of this matter.
Thank you.
Check date 3-27-91
CLD/mp
MACAREXT. CLD