ST8601-CS 901004DATE VIA: FRO~ RE-' COPPEI.~ PIIBI..IC ~ORK8 Director of Public Works October 4, 1990 Steven G. Goram, M. Shohre~and, ~cting City Engineer~ Larry D~, Construction Inspector /~ MacArthur North Extension - Inspe~on__ Fee (Tickler 10/1/90) ~ The calculated construction cost for street construction and storm drainage system on the above referenced project is $1,465,139.50, based on the contract documents supplied by the engineering firm of Carter and Burgess. The construction permit fee at 1.5% of $1,465,139.50 would be $21,977.00. The contract document construction time is based on 195 days from the issuance of the letter to proceed. The approximate construction inspection cost, for 195 days at an average of 3 hours per day spent on the job site, would be estimated as listed below: Inspection time Vehicle expenses Benefits Plan review Estimated inspection cost $ 7,800.00 600.00 2,400.00 3,500.00 $14,300.00 If I can be of further assistance, please let me know. MACARTHU.CLD