ST8601-CS 901001COPP~LL P~-BLIC WORKS MEMO~DUM October 1, 1990 Steven G. Goram, Director of Public Works Shohre Daneshmand, Acting City Engineer ~ ~. _ Larry Da '~ ~onstruction Inspector MacArthur North Extension - Inspection Fee (Tickler 10/1/90) The above referenced project calculated construction cost for street construction and storm drainage is $1,465,139.50, based on the contract documents supplied by the Engineering firm of Carter- Burgess. The construction permit fee of 1.5% of $1,465,139.50 would be $21,977.00. The construction time stipulated in the contract is 195 days from issuance of the letter to proceed. Based on the 195 construction day allowance, the construction inspection cost from September of 1990 to March 1991 would be approximately $11,000.00 If I can be of further assistance, please let me know. Thank you. CLD/bd MACINSPF.CLD