Meadows Addn 6-CS 891220December 20, 1989
COPPELL PUBLIC WORKS
~4EMORANDUM
TO:
FROM:
RE:
Larry Davis, Construction Inspector
Final Utility Walk Through f~s
Utility Crewleader Ted Dutt performed a final utility walk through
on the above referenced project on December 18, and has found the
following items to be deficient.
1. Samuel Blvd.and Marlee-Need 2' x 2' Concrete Pad on Valve
Stack
Marlee Drive- Lot 1 Reset Meter Box, Cut Off to close to Wall
of Box
Marlee Drive- Lot 2 Reset Meter Box, Cut Off to Close to Wall
of Box
4. Marlee Drive- Lot 25 Reset Meter Box, Cut Off to Close to
Wall of Box
5. Marlee Drive- Lot 28 Reset Meter Box, Cut Off to Close to
Wall of Box
6. Marlee Drive- Lot 32 Reset Meter Box, Cut Off to Close to
Wall of Box
7. Sta. 4 + 41 - Line S-1 Regrout Manhole Ring
Alendale- Lot 7 Reset Meter Box, Cut Off to Close to Wall of
Box I
9. Alendale- Lot 7 Repair Main Line Valve Stack and Pad
10. Woodmor Drive- Lot 17 Reset Meter Box, Cut Off to Close to
Wall of Box
11. Sta. 1 + 25 - Line S-6 Need Lid on Clean Out
12. Sta. 7 + 21 - Line S-1
Manhole Invert
13. Sta.
14. Sta.
15. Sta.
Out,
16. Sta. 4 + O0 - Line S-3
17. Sta. 1 + 43 - Line S-1
18. Sta. 18 + 28 - Line S-1
Regrout Manhole Ring and Clean Out
4 + O0 - Line $-1 Regrout Manhole Ring
3 + 50 - Line S-4 Regrout Manhole Ring
7 + 05 - Line S-3 Cut Pavement in Alley and Reset Clean
so that sewer pipe can be capped
Regrout Manhole Ring
Regrout Manhole Ring
Regrout Manhole Ring
Ail of the above referenced items will need to be addressed prior
to final acceptance of this project.
If you have any questions regarding this matter, please advise.
HLP/bb
xc: Steve Goram, Director of Public Works
MEADOWS6.HLP