ST9905DR-CS051128COPPELL
November 28, 2005
Chris Dixon
Craig Olden, Inc.
PO Box 5000
Little Elm TX 75068
RE: ST 99-05 Bethel Rd Drainage, Phase A
Dear Chris:
A pre-construction conference on the referenced project has been scheduled for
Thursday, December 1, 2005 at 2:00 p.m. in the second floor conference room in Town
Center at 255 Parkway Blvd.
Please notify the franchised utility companies, contractors, sub-contractors, testing lab
and any other interested parties so that they may have a representative present. If you
have any questions concerning this project prior to the scheduled meeting, feel free to
contact me at (972) 304-3685.
Sincerely,
Garreth Campbell, Construction Inspector
Office Phone: 972-304-3685
Fax: 972-304-3570
Ken Griffin, P.E., Director of Engineering & Public Works
Glenn Hollowell, P.E., Asst. Director of Public Works
Richard Gee, Texas CMT
RESPONSIBILITY FOR PRE-CONSTRUCTION
MEETING NOTIFICATION
The owner / owner's representative will be notified of the date, time and place of
the pre-construction meeting once it is scheduled by the Construction Inspector
assigned to the project.
It is the owner / owner representative's responsibility to notify the following
parties:
· Franchise Utilities (including but not limited to electric, gas, cable, &
telephone providers)
· Geotechnical firm
· Project Engineer
· Contractors or subcontractors for excavation, utility, & paving operations
· SWPPP representative