Park West CC(2)-CS 970421The City With A Beautiful Future.
P.O. Box 478
Coppell, Texas 75019
214-462-0022
April 21, 1997
James Koch, P.E.
Pacheco Koch Engineers, Inc.
9401 LBJ Freeway, Suite 300
Dallas, Texas 75243
Parkwest Commerce Center (Paragon Group)
Final Acceptance
Dear Mr. Koch
A final inspection of paving and utilities for the referenced project has been confu'med by
representatives of the City of Coppell.
The two-year maintenance bonds and as-built drawings have been received from the contractor.
Maturity on the bonds will be two years from the date of thi.~ letter. Maturity on the Erosion
Control Bond will also be two years from the date of this letter.
Sincerely,
Construction Inspector
c¢:
Ken Griffin, P.E., Dir. of Engineering & Public Works
Matt Cast, Supt. of Public Services
Greg Jones, Chief Building Official
Travis Crump, Fire Marshal
Doug Stevens, Engineering Technician
Ed. T. McGuire, Bob Moore Const., Inc. / FAX # (817) 640-1250
file/ldavis/paragon.fin